Delayed data center demand response: How quickly can ISOs add new loads?

Push for rapid grid connections and demand response solutions expose regional opportunities and challenges

byEnverus

CALGARY, Alberta (April 29, 2025) — Enverus Intelligence® Research (EIR), a subsidiary of Enverus, the most trusted energy-dedicated SaaS company that leverages generative AI across its solutions, has released a report examining how much load can be connected at different independent system operators (ISOs) without the buildout of new network infrastructure. The report also points out some considerations that limit the ability of data centers to commit to demand response, such as limited on-site generation capacity.

“With the data center boom comes high levels of competition. Data centers need to move fast and will therefore be looking for the quickest way to connect to the grid,” said EIR Principal Analyst Juan Arteaga.

“We estimate that the Pennsylvania-New Jersey-Maryland (PJM) and Midcontinent Independent System Operator (MISO) have the greatest opportunity for data centers to connect to the grid, as long as operators commit to load reduction during peak load periods. Demand response also means higher utilization of generation resources during off-peak periods — which is especially prominent in the California Independent System Operator (CAISO).”

Key takeaways from the report:

  • Data center operators seeking a first-to-market advantage are looking for faster grid connections than ISOs can currently offer. Demand response (DR) offers a method for them to utilize stranded infrastructure during off-peak periods.
  • More commitment to DR increases the load that could be added to the grid. EIR estimates that at 100 hours of DR (1.1% of the year), the ISOs that can add the greatest loads are PJM (11.9 GW), MISO (8.2 GW) and CAISO (5.8 GW).
  • Additions as a percentage of peak load are low in PJM (8%-18%) and MISO (8%-16%), but higher in CAISO (14%-28%), indicating greater resource utilization in CAISO despite fewer total additions.
  • PJM and MISO’s marginal load additions per hour of DR are the highest at 33 GW and 21 GW/hour, while CAISO’s is moderate at 13.9 GW/hour.
  • Since data centers demand high reliability and minimal downtime, they are less suitable for DR programs. In contrast, cryptocurrency mining is a good fit for DR as operations are more flexible.

Juan Arteaga will present these findings at EVOLVE 2025, a conference where visionaries converge to shape the future of energy. The conference will be held May 12-15, 2025, at the Hilton Americas in downtown Houston (1600 Lamar St, Houston, TX 77010).

Graph-of-potential-to-add-load-by-ISO

You must be an Enverus Intelligence® subscriber to access this report.

About Enverus Intelligence® Research:
Enverus Intelligence ® | Research, Inc. (EIR) is a subsidiary of Enverus that publishes energy-sector research focused on the oil, natural gas, power and renewable industries. EIR publishes reports including asset and company valuations, resource assessments, technical evaluations and macro-economic forecasts; and helps make intelligent connections for energy industry participants, service companies and capital providers worldwide. Enverus is the most trusted, energy-dedicated SaaS company, with a platform built to create value from generative AI, offering real-time access to analytics, insights and benchmark cost and revenue data sourced from our partnerships to 95% of U.S. energy producers, and more than 40,000 suppliers. Learn more at Enverus.com.

Picture of Enverus

Enverus

Energy’s most trusted SaaS platform — creating intelligent connections that uncover insights and opportunities to deliver extraordinary outcomes.

Related News

Enverus ranks top U.S. private E&P operators
News Release
ByJon Haubert

Enverus released its annual Top 100 Private E&P Operators list, ranking U.S. private oil and gas producers by production, well count and rig activity.

Enverus acquires PDS exchange assets, expanding its operating network across U.S. energy markets
News Release
ByJon Haubert

Enverus acquires four PDS Energy Information exchange platforms, expanding secure data exchange for completions, well, production and water data.

800 VDC rewrites AI data center power economics
News Release
ByJon Haubert

Enverus Intelligence® Research analyzes how 800 VDC architecture could lower AI data center electrical capex, improve facility efficiency and reduce copper intensity.

Enverus cuts U.S. EV adoption forecast due to federal policy changes and slower market growth
News Release
ByJon Haubert

Enverus Intelligence® Research’s latest EV forecast shows how slower U.S. adoption after federal tax credit changes shifts grid load timing, regional ISO exposure and ICE vehicle displacement through 2035.

At the cap, below CONE Why PJM’s capacity market needs a reset
News Release
ByJon Haubert

Enverus Intelligence® Research finds PJM’s current capacity market may not support financeable new gas generation at today’s capital costs. The report analyzes the capacity-price levels and bilateral contract structures needed to make new CCGT projects viable.

ERCOT Large Load Batch Zero Readiness
News Release
ByJon Haubert

Enverus Intelligence® Research analyzes ERCOT’s Batch Zero large-load qualification, estimating that 55 projects (21.7 GW) are positioned to meet the July 15 requirements while 62 projects (37 GW) are likely deferred to Batch 1+. The report outlines key deadlines, financial-security...

What’s next for the Strait of Hormuz?
News Release
ByJon Haubert

Enverus Intelligence® Research’s latest Strait of Hormuz outlook highlights a stocks-driven “higher for longer” setup, modeling OECD crude and product inventories falling from 2.82 Bbbl (YE25) to a 2.36 Bbbl trough in Q4 2026. The report also flags a potential...

Let’s make a deal Brent upgraded, Henry Hub downgraded
News Release
ByJon Haubert

Enverus’ latest Fundamental Edge report, “Let’s Make a Deal | Brent Upgrade, Henry Downgrade,” raises its 2H26 Brent forecast to $110/bbl on a late-June deal and gradual Strait of Hormuz reopening while maintaining a capped summer Henry Hub outlook and...

Class VI approvals build, submissions slow
News Release
ByJon Haubert

Enverus Intelligence® Research’s Class VI Update 1Q26 finds approvals building while submissions slow: three final permits issued in 2026 so far, five draft permits in 1Q26, and active Class VI injection capacity at 5.2 mtpa with forecasts above 100 mtpa...

Find Out How Enverus Can Help Your Business
Subscribe to the Energy Blog

A weekly update on the latest “no-fluff” insight and analysis of the energy industry.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Get Started

Sign up for our Blog

Ready to Subscribe?

Ready to Get Started?