Enverus Press Release - Enverus releases its 2024 Outlook

Signed, Not Delivered | Google Anchors Cape Station as FRVO Holds the Delivery Risk

GOOGL is now the anchor customer for FRVO’s Cape Station geothermal project in Utah. In its third-quarter update, FRVO identified the eight geothermal generating units, known as GeoBlocks, that will supply GOOGL’s 396 MW contract, with first deliveries expected in mid-2028. GOOGL also holds an option to add ~600 MW by June 2030, bringing its potential purchases to nearly 1 GW. The companies are pursuing the expansion as a behind-the-meter connection to a proposed Google data center campus in Beaver County. Cape Station has ~900 MW of fully contracted offtake, but only 33 MW is operating.

GOOGL is not alone. Enverus Intelligence® Research (EIR) tracks more than 1 GW of U.S. geothermal offtake signed against a ~1.5 GW buildout, with GOOGL accounting for 664 MW across FRVO and ORA projects (Figure 1). Under most of those contracts, the developer or utility absorbs the delivery risk. Buyers lock in clean, firm megawatts, while sellers assume the risk of producing them.

Bar chart of hyperscaler offtake by buyer, project and risk allocation

That risk has not been tested at scale. Cape Station’s design assumes water losses below 1%, compared with 27%-30% at FRVO’s Project Red pilot. Without infill drilling, thermal drawdown reduces well output to nearly zero within 20 years. Equipment supply is also tight. By 2028, FRVO’s annual demand for organic Rankine cycle turbines alone exceeds the industry’s ~300 MW/year of output.

FRVO closed Nov. 17 about 73% below its May peak and below our $15.71/share valuation. GOOGL’s contract demonstrates who will buy geothermal power. Cape Station’s water and production data will show how much of that power gets delivered.

This blog offers just a glimpse of the powerful analysis Power and Energy Transition Research delivers on the trending themes. Don’t miss the full picture.

Organic Rankine cycle turbines, now one of geothermal’s tightest supply bottlenecks, got their start in 1967 at Paratunka on Russia’s Kamchatka Peninsula. The world’s first geothermal binary plant used refrigerant to turn 80°C water, well below boiling, into about 680 kW of power. Google’s 396 MW Cape Station contract alone is about 580 times larger.

Research Highlights:

  • AI Chip Supply | EUV Capacity Caps Power at 37.0 GW
    Enverus Intelligence® Research uncovers how extreme ultraviolet (EUV) lithography capacity will limit AI accelerator supply, must be optimized between memory and logic, and ultimately caps chip power growth through 2030.

Upcoming Events

  • Roadshow: Equipment Constraints and Storage Revenue | Dec. 1–3 | Houston & Dallas | Request a Meeting

  • Webinar: Follow the Load: Where Data Centers Will Need Your Gas | Dec. 3 | 9:00–10:00 a.m. PCT | Online | Register Here

Can power keep pace with AI in 2027?

Load forecasts keep climbing. See where new capacity is getting built, and where it’s falling short.

Top Three Takeaways:

1: Who is the anchor customer for Cape Station geothermal power?

GOOGL is now the anchor customer for FRVO’s Cape Station in Utah. Its 396 MW contract will be supplied by eight GeoBlocks, with first deliveries expected in mid-2028. GOOGL also holds an option to add ~600 MW by June 2030, bringing potential purchases to nearly 1 GW.

2: Who bears the delivery risk on U.S. geothermal contracts?

EIR tracks more than 1 GW of U.S. geothermal offtake signed against a ~1.5 GW buildout. Under most of those contracts, the developer or utility absorbs the delivery risk. Buyers lock in clean, firm megawatts, while sellers assume the risk of producing them.

3: What could stop Cape Station from delivering its contracted geothermal power?

Cape Station has ~900 MW of fully contracted offtake, but only 33 MW is operating. Its design assumes water losses below 1%, compared with 27%-30% at FRVO’s Project Red pilot. Thermal drawdown also reduces well output to nearly zero within 20 years without infill drilling, and FRVO’s annual demand for organic Rankine cycle turbines exceeds industry output by 2028.

About Enverus Intelligence® | Research, Inc. (EIR)

Enverus Intelligence® | Research, Inc. (EIR) is a subsidiary of Enverus that publishes energy-sector research focused on the oil, natural gas, power and renewable industries. EIR publishes reports including asset and company valuations, resource assessments, technical evaluations, and macroeconomic forecasts and helps make intelligent connections for energy industry participants, service companies, and capital providers worldwide. See additional disclosures here.

Enverus Blog - 6 tax preparation tips for mineral and royalty managers

Before You File Taxes: What Mineral Owners Should Decide and When

With tax season upon us, mineral and royalty owners face the work of filing returns for their oil and gas income. The rules go beyond federal income tax. State severance taxes, property taxes and estate planning rules can each change the bill, and many of the most useful deductions are easy to miss. These six tips cover the issues that most often cost owners money or time.

1. Check how each interest was acquired

Mineral and royalty income is generally ordinary income, taxed at your regular rate. The picture changes when you sell. How an interest was acquired determines whether a sale produces capital gain or loss, and the cost basis is the number that drives the result.

If you received an interest for providing services, such as work as a geologist or landman, the tax treatment can differ from an interest you bought. The election rules around these interests have short deadlines, so talk with a CPA as soon as you acquire the interest. Waiting until filing season can mean missing the window.

2. Plan for inherited and gifted interests

Interests that pass to family members through an estate or a gift follow different rules, and the valuation work starts before the transfer. The federal estate and gift tax basic exclusion is $15 million per person for 2026 and $15.48 million for 2027, according to the IRS Revenue Procedure 2026-35. Most mineral owners will not reach that level, but a large portfolio can, and the value of mineral assets can rise quickly.

For the heir or recipient, the basis of an inherited interest is generally its fair market value at the date of death. A gift generally carries over the donor’s original basis. Keep the estate valuation, the appraisal and any gift documentation with the acquisition records, because they are the evidence for the basis you report later.

3. Report income by lease, not just by operator

Mineral and royalty revenue often comes from several operators and many leases. Summary 1099s can be enough for an owner with income from one lease. For owners with income from many leases, reporting by lease or property gives a clearer picture of what each one produces and makes it easier for a CPA to check the return.

Tracking this by hand is slow, which is why many owners move to a system that organizes statements by operator and property. EnergyLink® can bring statements from many operators into one place, so the lease-level picture is ready when your CPA asks for it.

4. Estimate severance taxes before the year closes

Severance tax is charged by most producing states on the value of oil, gas and condensate produced. Rates vary by state and by product, and some states set rates that change each year. Owners who hold interests in several states can face several different rules.

Look up the current rates for each state where you hold interests, using the state’s tax agency. Then check whether your revenue statements show the severance tax that was deducted. Missing or incorrect deductions are easier to catch in December than in April.

5. Use cost depletion when it beats the standard deduction

The depletion deduction recognizes that producing a resource reduces the value of the asset. Most owners use the statutory percentage, which is a fixed rate applied to royalty income. In some cases, cost depletion produces a larger deduction. It is calculated from the cost basis of the interest and the remaining recoverable reserves, so it is more complex than the standard rate.

Cost depletion is worth comparing with the standard deduction each year, the same way you would compare itemized and standard deductions on a personal return. The calculation depends on accurate production and reserve estimates for each property. EnergyLink can help you pull the production and revenue history that cost depletion requires.

6. Question property tax values that look too high

Most mineral owners pay property tax on their producing assets, and the way those assets are valued differs by state. Some states base value on projected future income. Others use different methods. In every case, the assessed value can be higher than what the asset is worth.

If an assessment looks too high, you can often protest it. Protests work best when they rest on evidence, such as production history, revenue data and a reasonable estimate of fair market value. Note the protest deadline on the notice as soon as it arrives, because missing it usually closes the option for that year.

Start with the records

Every tip above depends on records that are complete and easy to find: statements, 1099s, acquisition documents, valuation reports and production history. Our mineral tax checklist lists what to gather, so the work is ready before the return, or the protest deadline arrives.

Enverus releases Top 50 Public E&P Operators of 2024

What Supply Chain Teams Get Wrong About Supplier Disputes

This is the eleventh installment in our series of blog articles dealing with source-to-pay and upstream oil and gas. Read the previous blog here.

The Short Version

Most supplier disputes aren’t really about the invoice. They’re about decisions made much earlier, when the bid was awarded, the order was placed, or the work was logged in the field without a clear record. Teams that treat disputes as a downstream problem spend their time resolving them after the fact. Teams that design the upstream process to prevent them, by carrying awarded terms into orders and capturing field work with evidence, see far fewer disputes reach the invoice stage at all.

Ask most supply chain leaders how they handle supplier disputes and you’ll hear about process. There’s a dispute log, an escalation path, a standard set of questions for the supplier, and a team that gets good at working through them. That work is necessary. But it’s also a sign that the organization has accepted disputes as a normal cost of doing business, something to manage rather than something to design out.

That’s the mistake worth examining. Disputes feel like an invoice problem because that’s where they surface. The supplier sends a bill, the bill doesn’t match what someone expected, and the conversation starts. But the mismatch usually started weeks or months earlier, in a decision nobody revisited.

The dispute shows up at the invoice, but the cause usually sits much earlier in the process.

Key Takeaways

Where do most supplier disputes actually start?

  • Upstream, usually. Terms that weren’t carried from the award into the order, orders placed without clear approval or price, and field work recorded by phone or on paper all create the gap that later becomes a dispute at invoicing.

Why does the invoice stage look like the source of disputes?

  • Because it’s the first moment the mismatch is visible to anyone outside the field. The invoice is where the disagreement becomes official, even though the decision that caused it was made much earlier.

What does preventing disputes upstream look like in practice?

  • Awarded terms flow into the price book and the order, approvals happen in the system before work starts, and field tickets carry evidence that can be checked against the agreement before anything is billed.

The Dispute Starts at the Award

Think about what happens after a sourcing event closes. The team agrees on pricing, scope, and terms with a supplier. Then the agreement has to live somewhere that the people placing orders can actually use. If it lives in a spreadsheet, a PDF, or someone’s inbox, the rate on the next purchase order depends on who remembers it and who can find it.

That’s where the first gap opens. A rate might get keyed into the system incorrectly. A part number gets matched to the wrong line. A scope change that was discussed on a call never makes it back into the terms. None of these feels like a big deal when it happens, and none of them triggers an alarm. They just set up a mismatch that will surface later, when an invoice arrives at a rate nobody recognizes.

Preventing that starts at the award, not at the invoice. When negotiated pricing is turned into a validated price book that the order process can reference directly, the rate on the order is the rate that was agreed. The supplier and the operator are working from the same playbook from the start, and most of the arguments that would have followed never begin.

Where Orders Can Stop a Dispute Before It Starts

An order is the last clean chance to prevent a dispute before work begins. Once the crew is on site and the job is underway, the options narrow. The order is where you decide whether the spend is approved, whether it fits the agreed terms, and whether it has the right coding.

Our ordering solution is built around that moment. Purchase orders are tied to the price book, coding is captured when the order is issued, and approval workflows run in the system rather than in a side email chain. The intent is to stop unapproved or off-contract spend before work starts, so the supplier isn’t left guessing whether a job was authorized and the operator isn’t left guessing what it agreed to pay. An order that carries the right price and the right approval is much harder to dispute later, because the record of what was authorized already exists.

It’s worth being clear about the scope here. The approval and PO controls are what keep spend inside the agreed terms. How strictly they apply depends on how an organization configures its policies, so the protection is only as tight as the rules an operator sets.

Field Tickets as Evidence

Many of the disputes that reach the invoice stage come down to the same question: can anyone prove the work happened as described? When field tickets are paper, phone-in, or handwritten, the answer is often “sort of.” Hours are estimated. Locations are vague. Attachments never make it into the file. When the invoice arrives, the operator has nothing solid to check it against, and the supplier has nothing solid to point to.

Our ticketing solution changes what the record looks like. Field tickets are captured digitally, with GPS and geofencing, route information, hours, attachments, and supplier input in one place. Those tickets can be checked against the order and the contract before anything is billed, with automatic rate checks and three- and four-way matching run before payment. A discrepancy that would have turned into an argument becomes a flag that someone can look at while the work is still fresh and the supplier is still engaged.

That’s the practical difference. Instead of reconstructing what happened after the bill arrives, the evidence is already there when the invoice shows up. Most disputes don’t survive that kind of record, because the question of what was done and what it cost has already been answered.

Preventing Disputes Upstream

The shift that matters isn’t a new dispute process. It’s catching problems at the point where they start, not where they land. If the award carries into the order, the order carries the right approvals, and the field work produces evidence, then the process itself keeps most mismatches from forming.

That doesn’t remove the need for a dispute process. Some disagreements are genuine, and they deserve a real conversation. But the volume that reaches that conversation drops sharply when the upstream steps are doing their job. The team stops spending its best hours on recovery and starts spending them on the handful of cases that actually need judgment.

For supply chain leaders, that’s the reframe worth making. The question isn’t how to resolve disputes faster. It’s how to build a process where fewer of them are created in the first place.

Frequently Asked Questions

What causes most supplier disputes in oil and gas?

  • Most supplier disputes trace back to decisions made upstream: awarded terms that didn’t carry into the order, purchases placed without clear approval, and field work recorded without solid evidence. The mismatch usually becomes visible at invoicing, but it was created earlier.

How can operators prevent supplier disputes?

  • By designing the upstream process to prevent mismatches. That means carrying negotiated pricing into a price book that orders reference, requiring approvals before work starts, and capturing field tickets digitally so they can be checked against the agreement before payment.

What is the role of the purchase order in preventing disputes?

  • The purchase order is the last clean point to confirm that spend is approved and matches the agreed terms. With price-linked orders and in-system approvals, the record of what was authorized exists before the work begins, which makes later disagreements easier to resolve or avoid.

How do digital field tickets reduce disputes?

  • Digital tickets capture what was done, when, where, and by whom, with attachments and supplier input in one record. Checking that record against the order and contract before invoicing means discrepancies surface early, while they’re still easy to correct.

U.S. natural gas prices face power demand drag

The Chip Ceiling | PPL’s Data Center Queue Outruns Chip Supply

Third-quarter earnings season has brought a flurry of data center announcements. PPL Corp. said its pipeline of advanced-stage data center projects in PJM grew 3.5 GW to 35.3 GW in its Q3 earnings update, its 11th consecutive quarterly increase. Chip supply will make that pipeline hard to fill.

Chip supply is the largest bottleneck to AI expansion, and extreme ultraviolet (EUV) lithography is the binding step. Based on EUV output caps, Enverus Intelligence® Research (EIR) forecasts that AI chips shipped in 2030 will add 37 GW of thermal design power (TDP), the power the chips themselves draw (Figure 1). Including server and cooling loads, that supports 50.9 GW of nameplate data center capacity. The number of EUV passes required per chip will increase 4.8x from 2024 to 2030, limiting unit growth even as processing capacity rises.

PPL’s queue alone equals ~95% of that 37 GW, which is a stretch. In our 3Q26 Data Center Capacity Forecast, which draws on chip constraints, hyperscaler capex guidance and high-confidence projects, we estimate ~2 GW of capacity in the PPL zone across two campuses. Project stage and contracted offtake, not pipeline size, determine how much of the pipeline reaches commercial operation.

This blog offers just a glimpse of the powerful analysis Power and Energy Transition Research delivers on the trending themes. Don’t miss the full picture.

Strict export bans keep Chinese firms from buying complete EUV machines from ASML, so some reportedly piece together salvaged parts, but without ASML’s calibration software and assembly know-how, an EUV machine’s 100,000-plus components can’t reach the stability needed to make chips.

Research Highlights:

  • Coreweave NAV | Credit Where It’s Due
    Enverus Intelligence® Research examines CRWV using a sum of parts analysis to get a total net asset value per share.
  • AI Chip Supply | EUV Capacity Caps Power at 37.0 GW
    Enverus Intelligence® Research uncovers how extreme ultraviolet (EUV) lithography capacity will limit AI accelerator supply must be optimized between memory and logic, and ultimately caps chip power growth through 2030.
  • New York’s Storage Credit Conundrum | Delivered Reliability Doesn’t Scale With Duration
    Enverus Intelligence® Research analyzes which battery energy storage system duration – four-, six- or eight-hour – is most cost effective and delivers the most value under the New York State Energy Research and Development Authority’s Index Storage Credit solicitation.

Top Three Takeaways:

1: How much AI chip power will EUV lithography support by 2030?

Based on EUV output caps, EIR forecasts that AI chips shipped in 2030 will add 37 GW of thermal design power (TDP), the power the chips themselves draw. Including server and cooling loads, that supports 50.9 GW of nameplate data center capacity. EUV passes required per chip will increase 4.8x from 2024 to 2030, limiting unit growth even as processing capacity rises.

2: How big is PPL’s data center pipeline in PJM?

PPL said its pipeline of advanced-stage data center projects in PJM grew 3.5 GW to 35.3 GW in its Q3 earnings update. That is its 11th consecutive quarterly increase. The queue alone equals ~95% of the 37 GW of AI chip power EIR expects to ship in 2030.

3: How much data center capacity does EIR expect in the PPL zone?

In its 3Q26 Data Center Capacity Forecast, EIR estimates ~2 GW of capacity in the PPL zone across two campuses. The forecast draws on chip constraints, hyperscaler capex guidance and high-confidence projects. Project stage and contracted offtake, not pipeline size, determine how much of the pipeline reaches commercial operation.

About Enverus Intelligence® | Research, Inc. (EIR)

Enverus Intelligence® | Research, Inc. (EIR) is a subsidiary of Enverus that publishes energy-sector research focused on the oil, natural gas, power and renewable industries. EIR publishes reports including asset and company valuations, resource assessments, technical evaluations, and macroeconomic forecasts and helps make intelligent connections for energy industry participants, service companies, and capital providers worldwide. See additional disclosures here.

Enverus Intelligence® Research Press Release - Class VI applications signal slowdown

Canada’s Budget Bets on Electricity While Offline Supply to Keep Oil Prices Elevated

Canada’s new federal budget puts electrification at the center of its energy agenda, with a plan to double national generation by 2050. Meanwhile, roughly 8 million barrels per day of supply remains offline, and we still expect Brent to average around $100 per barrel next year.

Trade the facts, not the noise. 

Get energy fundamentals, price drivers, and risk signals in your inbox monthly.

Electricity Takes Center Stage in the Federal Budget

The budget’s energy story is about the grid. The proposal to double Canada’s electricity generation by 2050 pulls most of the policy attention away from oil and gas. Net zero remains the stated target, but the emphasis has moved to building generation capacity.

The budget includes about $600 million for electric vehicle (EV) chargers and a renewed incentive of up to $5,000 on eligible vehicles, depending on the program. EV sales stalled after earlier grants were withdrawn, so we expect the reinstated incentive to revive demand. For oil and gas producers, the most direct benefit is a tax break that helps project returns.

Net Zero Is Slipping, and the Gap Is Widening

Canada is falling short of its emissions path. The country is tracking about 28% below 2005 levels by 2035, short of its reduction target of 40% to 45%. Few countries are on track, and The Economist’s cover declaring net zero dead captured the broader skepticism about the goal.

The budget’s continued reference to net zero signals that the target still guides policy, even though reaching it requires far more effort. For energy planners, that gap makes electricity expansion the most realistic lever for emissions progress.

LNG Canada Gives Ottawa a Reason to Court Southeast Asia

LNG Canada Phase 2 is set to roughly double Canada’s export takeaway capacity. Almost 40% of Canadian LNG exports last year landed in South Korea, with Japan also a major destination and some volumes reaching China. A cargo from the Kitimat, B.C., plant reached the Philippines earlier this spring, giving Southeast Asia an early foothold.

Doubling capacity means the export customer base has to widen, and Southeast Asia is the logical place to look for new long-term buyers. We expect Prime Minister Carney’s visit to Manila may bring more detail on that outreach, including any energy-linked trade or tax incentives. Canada’s appeal as a reliable supplier grows as global buyers look for optionality, and that appeal is already showing up in capital investment interest.

Eight Million Barrels a Day Keeps the Oil Market Tight

Oil prices have pulled back by $20 to $30 per barrel since the U.S. midterms, with Brent in the mid-$90s and WTI in the high $80s to low $90s. The declines reflect hopes that the United States will not order an attack on Iran, but the fundamentals have not loosened. The Houthis in Yeman again struck Saudi Arabia’s vital East-West pipeline, tankers continue to be attacked in the Strait of Hormuz and inventories remain low.

The supply deficit is substantial. The latest report from the International Energy Agency showed around 8 million barrels per day of supply offline, and strikes on Russian refining capacity had kept another 5 to 7 million barrels per day out of the market. With strategic reserves drawn down around the globe, demand has to do the balancing, which requires higher prices. Our base case forecasts Brent will average around $100 next year, with volatility along the way and no lasting relief until the Strait situation is resolved.

Key Takeaways:

Why is electrification the centerpiece of Canada’s budget?

The budget aims to double national electricity generation by 2050, which makes power infrastructure the core priority. It keeps net zero as a target and adds about $600 million for EV chargers plus an incentive meant to revive EV sales. For oil and gas, the main benefit is a tax break.

What is the significance of LNG Canada’s expansion for Southeast Asia?

LNG Canada is set to nearly double the country’s export takeaway capacity, so it needs buyers beyond South Korea, Japan and China. Southeast Asia is a logical target, and the Philippines has already received a cargo. Prime Minister Mark Carney’s trip this month may bring more detail on energy partnerships and trade.

What factors are preventing oil prices from falling further?

Around 8 million barrels per day of supply remains offline, and Russian refining disruptions add 5 to 7 million barrels per day. Inventories are low and strategic reserves are being drawn down, so demand must eventually balance the market at higher prices. Continued attacks on oil tankers and Saudi Arabia’s East-West pipeline keep risk premiums in place.

About Enverus Intelligence® | Research, Inc. (EIR)

Enverus Intelligence® | Research, Inc. (EIR) is a subsidiary of Enverus that publishes energy-sector research focused on the oil, natural gas, power and renewable industries. EIR publishes reports including asset and company valuations, resource assessments, technical evaluations, and macroeconomic forecasts and helps make intelligent connections for energy industry participants, service companies, and capital providers worldwide. See additional disclosures here.

Enverus Press Release - The surprisingly balanced global LNG market

Midterm Voters Back Limits on Data Centers. What Investors Need to Know.

With local voters approving data center restrictions in 44 of the 45 local elections with results, the midterms made one thing clear: opposition isn’t confined to one community. It crosses party lines, and decisions about data center policy and grid-upgrade costs are playing out at the state and local levels.

A tally of local referendums tracked 47 local data center referendums across 44 municipalities in 12 states. Results were final for 45: voters approved restrictions in 44 of those votes, while results for the other two referendums were still pending. The results echoed concerns visible before the election: a University of Pennsylvania Annenberg Public Policy Center survey found that majorities of Democrats, Republicans and independents opposed new data centers in their communities.

Whether Tuesday’s results change total U.S. data center capacity over the long term remains unclear. Their nearer-term significance is at the project level: local opposition and state or local policy can shape where developers pursue sites and which opportunities investors consider viable. Enverus Intelligence® Research (EIR) tracked project schedules for more than six months and found that expected in-service timing shifted later for 50% of under-construction data center load planned for 2026 and 52% of under-construction data center load planned for 2027. For investors, delays affecting this much planned capacity could push expected cash flows further out.

“Every month of delay directly impacts the return on a project.”

Tuesday’s results add a local-policy risk to those already shifting timelines: whether local opposition will add further delays or affect which projects can advance.

To account for projects that stall or are canceled, investors and developers may need to keep more sites in play. In the ”Election Aftershocks: Reading the Midterms Through a Power Lens” webinar, Ian Nieboer, Head of Power and Energy Transition Research (PETR), and Carson Kearl, senior analyst who leads EIR’s data center research, discuss this strategy and what it means for investors.

EIR estimates developers hold land for 272 GW of data centers, while only about 5% of entitled parcels ever reach energization. That gap makes project stage and a credible path to power more useful indicators for investors than headline pipeline capacity.

There’s like 500 things that have to go right, and any one of them has to go wrong to stall the execution and delivery on one of these projects.

Power contracts add another test of project economics. EIR found that eight of ten large-load tariffs require payment for 70% to 90% of contracted demand for 10 to 20 years. If a project ramps more slowly or uses less power than expected, those commitments may affect returns and shape how risk is shared among developers, customers, and counterparties.

Local votes, project timelines and long-term power contracts are reshaping where and whether data centers get built. Ian and Carson dig into what that means for investors in the full conversation. You don’t want to miss this.

Every $5 billion you spend on LNG infrastructure nets you the same amount of incremental gas demand as $500 billion spent on AI infrastructure. The difference has nothing to do with the energy. The difference has everything to do with the top of this figure, the full stack, the chips.

Listen to the podcast: Election Aftershocks: What the Midterms Mean for Data Centers and Power

Join us for a deeper look at how these pressures vary across markets and affect data center development and power markets.

About Enverus Intelligence® | Research, Inc. (EIR)

Enverus Intelligence® | Research, Inc. (EIR) is a subsidiary of Enverus that publishes energy-sector research focused on the oil, natural gas, power and renewable industries. EIR publishes reports including asset and company valuations, resource assessments, technical evaluations, and macroeconomic forecasts and helps make intelligent connections for energy industry participants, service companies, and capital providers worldwide. See additional disclosures here.

Enverus Press Release - Enverus releases Investor Analytics: Refined, actionable financial insights at your fingertips

Speed Sells | Reciprocating Engine Backlogs Hit Record Highs

BTM Gas Generation Installed in 2026-30 by Technology

Last week, three reciprocating engine original equipment manufacturers (OEMs) reported third-quarter earnings, ending the period with record reciprocating engine backlogs. INIO, CAT and WRT1V each reported all-time-high order books in late October, with INIO’s equipment backlog rising 142% year over year to $8 billion. By comparison, GEV added a net 6 GW of gas turbines under contract in the third quarter, a slight cooldown from the double-digit quarterly growth recorded earlier in the year.

GEV’s order slowdown could reflect a shift in customer orders toward modular technologies offering a quicker path to power. As utilities and grid operators face record load interconnection requests and longer delays, data centers and other industrial facilities are generating their own power behind the meter (BTM) using technologies such as reciprocating engines to bypass grid constraints and accelerate deployment.

For BTM projects, speed can be a deciding factor in technology selection. Enverus Intelligence® Research (EIR) estimates the majority of gas-fired BTM capacity added through 2030 will come from modular technologies such as reciprocating engines, small- and medium-frame turbines and fuel cells, which offer a time-to-power edge over large-frame gas turbines. Lead times for large-frame gas turbines have stretched beyond five years, and a large-frame combined-cycle project can take up to 80 months from order date to commercial operation. By comparison, reciprocating engines can come online within 24 months of an order.

That speed advantage is showing up in OEM order books. As developers race to bring power online, record reciprocating engine backlogs and slowing contract growth for large-frame turbines signal that developers are increasingly prioritizing quicker paths to power.

Please contact intelligence@enverus.com if you have any issues accessing links or if you would like to learn more about Enverus products and services.

This blog offers just a glimpse of the powerful analysis Power and Energy Transition Research delivers on the trending themes. Don’t miss the full picture.

The 14-cylinder Wärtsilä-Sulzer RTA96C, the world’s largest reciprocating engine, weighs over 2,300 tonnes and stands four stories tall. Its 300-tonne crankshaft rotates at just 102 rpm, yet the two-stroke turbocharged diesel engine produces about 80,000 kW, enough to propel the largest container ships.

Research Highlights

  • Data Center Water Use | Setting the Record Straight – A first-principles analysis of data center water consumption finds that frontier large language model inference uses far less water than the same amount of spending on retail electricity, almond milk or golf. On a land-use basis, a modern hyperscale campus consumes less water per acre than an average U.S. golf course.

  • Class VI Update 3Q26 | Clearing the Queue From Both Ends – In this quarterly report series, EIR provides an overview of recent changes to Class VI wells associated with CCUS projects in the U.S. Leveraging the Enverus FOUNDATIONS® – Carbon Innovation Wells database, we cover new Class VI applications, changes to permit status, permit approvals and newly disclosed project details.

Upcoming Events

  • Webinar | Skipping the Queue: The Supply Chain Powering Behind-the-Meter Generation | Nov. 5 at 10 a.m. (CST) | Online | Register Here

  • Roadshow | The Energy Gap and Data Center Demand | Nov. 10-12 | New York and Northeast | Request a Meeting

  • Webinar | Renewable Diesel at the Crossroads: Supply Gaps, Policy Shocks and the North America-Europe Balance | Nov. 12 at 10 a.m. (CST)  | Online | Register Here

Top Three Takeaways:

1: How much data center load is expected to be served by behind-the-meter generation?

Enverus Intelligence® Research (EIR) estimates the majority of gas-fired BTM capacity added through 2030 will come from modular technologies such as reciprocating engines, small- and medium-frame turbines and fuel cells. These technologies offer a time-to-power edge over large-frame gas turbines.

2: Why are developers favoring reciprocating engines over large-frame gas turbines?

Lead times for large-frame gas turbines have stretched beyond five years, and a large-frame combined-cycle project can take up to 80 months from order date to commercial operation. Reciprocating engines can come online within 24 months of an order.

3: What do record reciprocating engine backlogs signal about the market?

Record reciprocating engine backlogs and slowing contract growth for large-frame turbines signal that developers are increasingly prioritizing quicker paths to power. INIO’s equipment backlog rose 142% year over year to $8 billion.

About Enverus Intelligence® | Research, Inc. (EIR)

Enverus Intelligence® | Research, Inc. (EIR) is a subsidiary of Enverus that publishes energy-sector research focused on the oil, natural gas, power and renewable industries. EIR publishes reports including asset and company valuations, resource assessments, technical evaluations, and macroeconomic forecasts and helps make intelligent connections for energy industry participants, service companies, and capital providers worldwide. See additional disclosures here.

enverus-power-and-renewables-grid

Power Analyst for PRISM: A Faster Path From Question to Insight

Power market decisions rarely hinge on one data point. Effective power market analysis requires teams to connect interconnection, capacity, site constraints and market activity. Finding and bringing those signals together takes time away from evaluating the opportunity.

Power Analyst gives PRISM® users a new place to start: the question they need to answer. Ask in plain language, and it brings relevant data from your PRISM subscriptions into a structured response you can explore further.

Start with the question. Follow where it leads.

Instead of first deciding which dataset to open, describe what you’re trying to understand. For example: What should I consider when evaluating a site near this substation?

Power Analyst brings the relevant subscribed data into the conversation. But a question about a potential site rarely stops at the substation. You may want to understand nearby interconnection activity, available parcels, buildability, market conditions or other factors that could affect the opportunity.

Power Analyst keeps the conversation’s context, so users can investigate a result, narrow the geography or change an assumption without starting over. Each answer becomes a starting point for the next question, helping you build a more complete view of the opportunity while staying connected to the data behind it.

From question to decision in four steps.

Power Analyst does the work of identifying, connecting and organizing the relevant data so you can focus on the analysis and decision.

Power Analyst PRISM Steps: Ask > Connect > Explore > Act

How teams across the industry use Power Analyst

From assessing potential sites to weighing market opportunities, every team approaches power market analysis with different questions. Power Analyst helps them explore the PRISM data tied to those decisions.

  • Power developers screen parcels, check interconnection, and track competing project activity. Power Analyst weighs all three together in one conversation.

  • Large load developers match large-load needs to capacity, nearby power, and buildability. Follow-up questions compare candidate sites without rebuilding the analysis.

  • Business development teams track active developers and projects. Power Analyst surfaces current activity by region so outreach lands at the right time.

  • Financial teams test the competitive, buildability, and risk inputs behind a valuation. Power Analyst returns referenced answers and runs scenarios, so each conclusion can be traced before you price a deal.

Go beyond a generic AI answer

More than 2,800 organizations are already transforming their workflows with Enverus AI, built on more than 25 years of energy intelligence. Power Analyst builds on that foundation, helping teams navigate and synthesize the depth of Enverus data and expertise to arrive at insight faster.

Generic AI tools can produce an answer, but they don’t have access to the proprietary power market data behind the decision. Power Analyst works with the Enverus data included in your PRISM subscriptions, with responses referencing the underlying data that supports the analysis. That means you can explore the answer, understand what supports it and apply your own expertise before you act.

You bring the market question. Power Analyst helps you explore the relevant data. Your expertise turns that analysis into a decision.

Spend less time navigating. More time evaluating.

PRISM brings together the power market data behind complex analysis. Power Analyst makes it easier to put that intelligence to work.

Instead of beginning with “Which dataset do I need?” you can begin with “What do I need to know?”

The goal isn’t AI for AI’s sake. It’s a faster path from question → analysis → decision.


Ready to start your next PRISM workflow with a question?

Natural gas power M&A premiums double as data center demand and capital costs transform U.S. energy market

PJM and MISO Winter Outlook: A Mild Season With Thin Margins

Based on the Enverus Intelligence® Research Winter Power Market Outlook webinar for PJM and MISO, presented by Kenneth Curtis, Director of Power Analytics, and Rob Allerman, Sr. Director of Power Analytics.

A record-strength El Niño points to a warm winter across PJM and MISO. Warm doesn’t mean calm. PJM’s 2028/2029 capacity auction cleared at the price cap for the third straight year, and MISO hit its $10,000/MWh cap on Sept. 2 without a single unit trip. Enverus Intelligence® Research (EIR) sees mild weather setting the base case this winter, with thin reserves setting the risk.

A record El Niño sets up a warm winter

EIR’s analog years are 2015/16 and 2023/24, which average +1.6 on the Relative Oceanic Niño Index (RONI). The global climate model statistical average for December through February is +3.1h, and the models show record-high El Niño conditions. A supercharged jet stream should keep wind above average.

In PJM, EIR’s forecast is for a warmer-than-average winter than last year. In December 2015, only one day fell below freezing in Washington, D.C. and Philadelphia. January should be cooler than December but still warmer than average, and February could run 10 to 15 degrees above average, especially in Chicago.

MISO looks similar. December 2015 was the warmest on record for Indianapolis and Detroit. EIR expects January to follow a similar trend & have below average load,. February should be warm again.

PJM: little cushion left in the system

PJM’s 2028/2029 Base Residual Auction cleared at the $325/MW-day price cap, the third straight capped auction. It’s also the second consecutive auction to clear short of the reliability requirement: about 6,517 MW short in 2027/2028, the first physical shortfall in the market’s 19-year history, and 6,831 MW short in 2028/2029.

PJM capacity auction clearing prices ($/MW-day, UCAP).
PJM capacity auction clearing prices ($/MW-day, UCAP). The last three auctions cleared at the price cap.

Through October, PJM has logged about 300 five-minute intervals with ORDC shortage pricing in 2026, a pattern consistent with a thinner margin. More evidence of this pattern is in Western Hub (WH) heat rates, which are spiking higher and staying elevated longer each year.

PJM Western Hub implied heat rate duration curve, Jan. 1 to Sept. 17 of each year.
PJM Western Hub implied heat rate duration curve, Jan. 1 to Sept. 17 of each year (WH day-ahead 7×16 LMP divided by Tetco M3 day-ahead gas).

Year-over-year load growth is near 2%. EIR’s winter forecast assumes 3% to 4% load growth, a strong El Niño and Dominion back in RGGI, adding a $3 to $5 premium at WH.

On supply, Eddystone (760 MW) is projected to deactivate Nov. 20, 2026, contingent on no seventh DOE order extension, and Elwood’s 2026 retirement was withdrawn. The Chanceford–Doubs 500 kV line is expected in service in June 2027. EIR sees no 2026 pricing impact and a modest bearish lean on WH and DOM for 2027 and beyond.

Transmission outages shape the congestion picture:

  • December: The Meadowbrook–Loudon outage (Dec. 2–17) adds bullish congestion for WH from MORR-LOUD. Marysville corridor outages in Ohio (Dec. 2–8) are bullish for AD Hub.

  • January: The Mt. Storm–Prunty outage (Jan. 4 to Feb. 1) sets up bullish WH through BED-BLA or AEP-DOM congestion.

  • February: The Goose Creek transformer outage in Data Center Alley (Feb. 1 to April 16) opens the door to bearish WH congestion.

PJM price view: the right tail is the story

PJM implied heat rateBearishExpectedBullishForward
December16.719.634.217.5
January10.013.024.712.0
February12.714.728.713.2

December is back to being undervalued, with meaningful right-tail risk tied to reserve margins, congestion and structural load growth. January remains EIR’s preferred winter month, with upside from cold weather and BED-BLA congestion. In February, our base case sits near the bend in the stack. A colder stretch, weaker wind or higher outages can push PJM into a much steeper part of the curve.

MISO: September showed how fast energy goes to the cap

On Sept. 2, MISO printed the $10,000/MWh cap for multiple intervals between 6 and 8 p.m. ET. No unit tripped, and wind didn’t miss forecast. Load ran 4,300 to 5,700 MW above the day-ahead forecast, about 18 GW of solar dropped off by HE20 and imports weakened. Indiana Hub real-time prices averaged $4,118.32 in HE20, against $257 day-ahead.

MISO on Sept. 2: load ran above forecast as solar dropped off, and Indiana Hub real-time prices spiked to $4,118.32/MWh in HE20.
MISO on Sept. 2: load ran above forecast as solar dropped off, and Indiana Hub real-time prices spiked to $4,118.32/MWh in HE20.

The same mechanism drove the Sept. 17 event. Reserve scarcity pulled energy prices up through MISO’s co-optimization, not the other way around. As evening ramps steepen and reserve margins thin, that exposure becomes a recurring feature rather than a one-off. Weather-normalized demand growth averaged +2.3% on-peak and +3.2% off-peak over the most recent week, which keeps tightening reserves around the edges.

Retirements now hinge on the courts. On Sept. 11, the D.C. Circuit vacated DOE’s first Campbell order, ruling DOE exceeded its 202(c) authority. The current order holds Campbell online through Nov. 14, 2026, but a seventh extension now carries real legal risk.

Congestion risks to watch include a 345 kV outage on SPP’s S3455–S34740 line in December (bullish Minnesota Hub, bearish Indiana Hub), Oneida–Majestic work starting Jan. 4 (bullish Michigan Hub) and Gibson–Petersburg work starting Feb. 1 (bullish Indiana Hub).

MISO price view: forwards have caught up

MISO implied heat rateBearishExpectedBullishForward
December14.819.022.817.9
January12.616.819.318.0
February9.916.419.417.7

Winter forwards have largely repriced September’s scarcity premium, and EIR’s expected values sit relatively close to the market. December looks reasonably valued, with upside if it turns colder or less windy. January forwards sit modestly above our expected value, and February is largely aligned with our outlook.

What to take into the winter

  • EIR expects a warmer-than-average winter with El Niño.

  • WH is the risk. Heat rates keep spiking and staying elevated.

  • MISO reserves are tightening into winter. Sept. 2 and Sept. 17 showed how fast energy goes to the cap.

Want to stay ahead of how PJM and MISO trade this winter? Learn more about our power trading solutions.

About Enverus Intelligence® | Research, Inc. (EIR)

Enverus Intelligence® | Research, Inc. (EIR) is a subsidiary of Enverus that publishes energy-sector research focused on the oil, natural gas, power and renewable industries. EIR publishes reports including asset and company valuations, resource assessments, technical evaluations, and macroeconomic forecasts and helps make intelligent connections for energy industry participants, service companies, and capital providers worldwide. See additional disclosures here.

power-grid-congestion

ERCOT and SPP Winter Outlook: Wind Decides the Big Days

Based on the Enverus Winter Power Market Outlook webinar for ERCOT and SPP, presented by Adam Jordan, Director of Power Analytics.

ERCOT has produced only 15 to 30 hours above 60 GW of net load in each of the last few winters. Winter in Texas is event-driven, and Enverus Intelligence® Research (EIR) expects the difference between a $100 day and a $1,000 day to come down to wind. This winter adds a record El Niño, which brings mild temperatures but also storms that cut into solar output. In SPP, load growth is outpacing capacity additions.

ERCOT implied heat rate vs. net load, all winter hours (December through February), 2022/23 to 2025/26. Few winter hours reach the steep end of the curve.
ERCOT implied heat rate vs. net load, all winter hours (December through February), 2022/23 to 2025/26. Few winter hours reach the steep end of the curve.

An El Niño for the ages

EIR’s analog years are 2015/16 and 2023/24, which average +1.6 on the Relative Oceanic Niño Index (RONI). The global climate model statistical average for December through February is +3.1, and the models show record-high El Niño conditions. The pattern points to a warm north and cooler anomalies in the south, and a supercharged jet stream should keep wind above average.

In ERCOT, EIR expects a stormy December with limited heating load. January should bring long stretches of mild or seasonal weather punctuated by one or two violent arctic outbursts, and their number, timing and location are the greatest risk to the forecast. The February analog years were mild and lacked significant cold events, another signal that cold risk concentrates in January. Gas prices stand out in the analog years: both mild winters ended with high storage, and average spot Henry Hub slid below $2.00. That isn’t a gas forecast. It’s a risk to power prices through lower marginal fuel costs.

ERCOT congestion has eased

The constraints behind LZ_WEST price strength have seen major mitigation, especially along the Midland-Odessa corridor, where Vealmoor-Koch and Morgan Creek-Navigation formerly dominated. Congestion into LZ_WEST has fallen sharply in 2026. Elsewhere, new 345 kV double circuits through Cruce effectively eliminate LaPalma and Weslaco-Heidelberg congestion.

Load growth holds near 5%

Annualized ERCOT load growth has measured just shy of 5% year to date. Large loads are showing up primarily in the NCEN and SCEN zones, and the large coastal load is new LNG capacity. We expect 2027 growth to continue at roughly 5%, and Batch Zero approvals in April 2027 set up higher growth in 2028.

Solar and battery projects continue to trend larger, which has changed long-established congestion patterns. WESTEX, for example, will bind more on-peak than off-peak because of solar. EIR expects 5 to 6 GW of new solar in 2027, a drop from the last couple of years, and about 2.4 GW of battery storage is under construction with 2027 first power.

ERCOT price view: January carries the risk

ERCOT implied heat rateBearishExpectedBullishForward
December9.09.49.610.4
January10.110.815.012.5
February9.510.211.213.2

December presents a tame entry to winter. We favor downside risks because December is historically low volatility. January holds the most risk for price strength of any winter month. Temperatures may be mild, but storms will diminish solar, and higher net load from weak solar is one of the primary paths to price strength. Add an isolated arctic outbreak and the bullish case comes into focus. In February, bullish risks relax as the chance of a high-impact storm diminishes quickly.

SPP weather: cold risk peaks in January

We expect warm anomalies in December to concentrate in the northern half of SPP, with below-average demand and the risk of a cold snap in the third or fourth week. January is the heart of winter, and the risk of an arctic intrusion is highest then. February looks wetter for Oklahoma and dry from Nebraska north, as a strong Pacific jet stays draped over Texas with occasional breakouts north.

SPP congestion: North Hub volatility continues

EIR expects North Hub volatility to continue throughout the winter. Strong heating demand will amplify outage impacts:

  • Weeping Water corridor, Nebraska (Oct. 23 to Dec. 18): Increased flow on NEBRCTY-SUB3456 is bullish for North Hub and bearish for South Hub.

  • Near Great Bend, Kansas (Jan. 4 to April 30, 2027): Increased flow on KNOLL1-NHAYS is bullish for South Hub and bearish for North Hub.

SPP load growth outpaces new capacity

SPP has about 2.5 GW of generation under construction, based on the Enverus PRISM® classification. SPP’s reserve margin is shrinking and will keep declining until 2028, according to SPP’s own outlook, which means more volatility in shoulder seasons.

SPP began publishing non-conforming (NC) load data in March. NC load is typically large, flat industrial and data center load. Monthly average NC load is up about 30% since March, or about 200 MW (20%) excluding newly reported KCPL. SPP winter implied heat rates have compressed over the last four winters, driven by fuel switching and gas costs, while the supply stack is essentially unchanged.

SPP monthly average non-conforming load by reporting balancing authority, 2026. Up about 30% since March.
SPP monthly average non-conforming load by reporting balancing authority, 2026. Up about 30% since March.

SPP price view: risks lean bearish

SPP South Hub implied heat rateBearishExpectedBullishForward
December7.611.712.312.3
January6.512.714.215.8
February6.511.812.414.5

Risks lean bearish in December, and our bullish scenarios only reach parity with current forwards, leaving little upside for South Hub to wrap up 2026. January holds risk for strong load from stormy skies in the south and arctic intrusions in the north, but we don’t expect strong or prolonged outbreaks, and our most bullish scenarios are still a few dollars short of the market. In February, market sentiment leans bearish relative to our base case.

What to take into the winter

  • An El Niño for the ages.

  • ERCOT’s reliance on solar introduces price risk in a stormy winter.

  • ERCOT congestion patterns remain at reduced intensity.

  • SPP’s load growth outpaces capacity additions.

Want to stay ahead of how ERCOT and SPP trade this winter? Learn more about our power trading solutions.

About Enverus Intelligence® | Research, Inc. (EIR)

Enverus Intelligence® | Research, Inc. (EIR) is a subsidiary of Enverus that publishes energy-sector research focused on the oil, natural gas, power and renewable industries. EIR publishes reports including asset and company valuations, resource assessments, technical evaluations, and macroeconomic forecasts and helps make intelligent connections for energy industry participants, service companies, and capital providers worldwide. See additional disclosures here.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Ready to Subscribe?

Ready to Get Started?