Power & Renewables

The Interconnection Queue: An Introduction

bySarp Ozkan

The interconnection queue is a collection of power generation and transmission projects requesting to connect to the power grid. Generation projects can be pre-construction, construction, built/non-operational and operating.

How do power developers submit projects to the queue?

As power developers start the process of new generation projects, they submit an interconnection request to the ISO to join the queue. An interconnection queue request would include data and documentation surrounding the project. This would include information such as project type, fuel type, net megawatt, location, operating data, synchronization date, point of interconnection, system impact study, builders, suppliers and more.

In addition to the interconnection request, a series of studies are completed to ensure the project that will potentially join the power network meets the ISO’s reliability, safety and facility standards, and is an overall best fit for the network.

What are the types of studies conducted?

  • System Impact Study (SIS) — An engineer evaluation of the point of interconnection.
  • Feasibility Study (FS) — The cost and impact a new project would have on the system.
  • Facilities Study (FAC) — The electrical configuration, price and schedule to complete interconnection.
  • Optional Interconnection Study (OIS) — The odds of other projects in the queue being withdrawn.

What has been approved and joined the power grid recently?

From 2007 to 2021, there has been an increase in renewable energy sources and demand.

graph-showing-interconnection-queue-projects-by-type-YOY
graph-showing-interconnection-queue-projects-by-type-YOY

With the increase in demand and adoption of renewable energy, the current queue is overflowing. Right now, there are more than 700 gigawatts panned across the seven ISOs with projected completion dates from 2022 to 2025.

Picture of Sarp Ozkan

Sarp Ozkan

Sarp Ozkan is VP of Commercial Product at Enverus. He joined Enverus through the acquisition of products and services from Ponderosa Advisors in 2016 and has more than 10 years of research and modeling experience in the upstream, downstream and power markets. Sarp has been a trusted energy expert for the media and for state regulatory bodies throughout the U.S. and has led consulting projects around many M&A and strategy related inquiries. He has presented at many commercial and academic conferences around the world and been published in several peer-reviewed journals. Sarp holds a Master of Science in Mineral and Energy Economics from the Colorado School of Mines, a Master of Science in Petroleum Economics and Management from the Institut Francais du Petrole (IFP School), and a Bachelor of Arts in Economics from the University of Chicago.

Subscribe to the Enverus Blog

A weekly update on the latest “no-fluff” insight and analysis of the energy industry.

Related Content
Enverus Press Release - Enverus releases Investor Analytics: Refined, actionable financial insights at your fingertips
Post
Power & Renewables
ByAlex Nevokshonoff, Senior Analyst, Enverus Intelligence® | Research (EIR) Contributor

Reciprocating engine backlogs surge as developers favor modular gas-fired BTM solutions for faster time-to-power and shorter lead times.

Natural gas power M&A premiums double as data center demand and capital costs transform U.S. energy market
Post
Power & Renewables, Power Trading+1
  • Utilities
ByEnverus

EIR’s PJM and MISO winter outlook: a record El Niño, capped capacity auctions, MISO scarcity risk and heat rate forecasts for Dec. through Feb.

Aging-power-plant_1418205261-1
Post
Power & Renewables, Power Trading+1
  • Utilities
ByEnverus

EIR’s ISO-NE and NYISO winter outlook: how NECEC and CHPE reshape Northeast spreads, plus RGGI costs, El Niño weather and heat rate forecasts.

EIR’s model shows powered-land can rise more than 20-fold in value as data center sites reach energization
Post
Power & Renewables, Power Trading+1
  • Utilities
ByEnverus

EIR’s CAISO and Mid-C winter outlook: how a stormy El Niño, record battery activity, EDAM vs. Markets+ and carbon prices shape Western power.

Time-to-power gap Big generation’s Achilles’ heel in the AI data center race
Post
Power & Renewables, Power Trading
ByEnverus

PJM has 113.6 GW of announced large-load capacity, far more than the 28.5 GW under construction. See what the gap means for reliability and planning.

U.S. natural gas prices face power demand drag
Post
Power & Renewables, Power Trading
ByEnverus

ERCOT data shows large loads ramping at different rates as solar and battery additions keep pace, with new supply expected to slow in 2027.

Enverus Press Release - Prioritizing renewable PPA offtaker targets proves more challenging than expected
Post
Power & Renewables
ByThomas Popa

Senate’s bipartisan permitting bill data centers grid interconnection could curb speculative queues and speed transmission buildout.

Enverus Press Release - Renewable diesel: Too much of a good thing?
Post
Data Centers, Financial Services+1
  • Power & Renewables
ByEnverus

Validate data center natural gas supply: check pipeline capacity, contracts, routing, and long‑term durability before you commit.

Enverus Press Release - How much production growth can North America deliver over the next decade?
Post
Power & Renewables
ByEnverus

See how Enverus called ERCOT's August 2026 coincident peak a day early and pinpointed the exact peak hour, beating ERCOT's own load forecast accuracy.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Sign up for our Blog

Ready to Subscribe?

Ready to Get Started?