Power and Renewables

Successfully Navigating the Interconnection Queue With Project Probability

byAmanda De La Rosa
March 5, 2024

Overwhelmed Interconnection Queue and High Project Attrition

In the rapidly evolving landscape of the power market, the interconnection queue stands at a critical juncture for new energy projects seeking to integrate with the grid. The recent surge in renewable energy projects has left the queue overwhelmed, with regulatory framework and infrastructure struggling to keep pace. The ability of the existing grid to accommodate new entrants without compromising reliability has proven a major challenge, driving up network upgrade costs while also increasing delays for projects waiting in the queue. The growing backlog and rising costs have left developers, traders, and the pace of the energy transition adversely impacted as the interconnection queue has turned into a bottleneck for the deployment of new energy sources.

Only a fraction of projects entering the interconnection queue reach final approval and construction. For PJM, more than 130,000 MW of proposed renewable energy projects have been withdrawn in the past 10 years; comparable cases can be observed for all other ISOs (Figure 1). There is a high attrition rate, with many projects ultimately withdrawing due to feasibility issues, budgetary constraints or regulatory hurdles. In addition to impeding the expansion of renewable energy, this bottleneck raises risk and uncertainty for investors and developers. At the end of 2023, more than 7,500 projects representing more than 1350 GW of generation and storage were seeking grid interconnection in the U.S. However, most of this proposed capacity ultimately will not be constructed. Historically, from 2007-2023, only an estimated 20% of projects requesting interconnection were able to reach commercial operation – 80% had withdrawn from the queue (Figure 2).

total-suspended-project-capacity-mw-across-each-iso-over-the-past-10-years
Figure 1. Total suspended project capacity (MW) across each ISO over the past 10 years
total-project-capacity-mw-by-project-status
Figure 2. Total project capacity (MW) by project status (operating and suspended) and interconnection request year across all seven ISOs (2007-2023)

Understanding the likelihood of a project’s completion is critical for asset developers and energy traders. Project feasibility, cost and timeline are all strongly impacted by queue position. Developers must navigate these uncertainties, balancing the potential returns and risks associated with the interconnection queue. Conversely, energy traders need to evaluate the impact of new projects on supply, prices and market dynamics. Ultimately, a project’s status in the interconnection queue is a valuable piece of intelligence as the integration of new generation capacity has the potential to shift energy markets significantly.

A New Way to Evaluate the Interconnect Queue: Project Probability

To counter the speculative nature of projects in the interconnection queue, Enverus PRISM®’s Project Tracking solution has added Project Completion Probability score, which provides insights into which power projects have a higher probability to be built. The project probability score is produced by a binary classification machine learning model that analyzes and predicts the probability of success of every renewable generation project in the interconnection queue across ISOs. The model is trained on all historically operating and withdrawn projects within a respective ISO, and dynamically assigns each project a likelihood using significant project factors such as status, capacity, owner and developer, etc. This score is continuously updated as the project progresses through the queue. Project Completion Probability scores can provide insight into identifying prime locations for project development. This map from PRISM displays all proposed projects in Virginia in the PJM Interconnection Queue (Figure 3). The light blue dots in the map below indicate a Project Completion Probability score over 50% likelihood of reaching commercial operations, while the red dots indicate all projects under a 50% likelihood, or less likely to reach commercial operations.

most-projects-in-pjms-interconnection-queue-in-virginia-have-a-high-likelihood-not-to-break-ground
Figure 3. Most projects in PJM’s interconnection queue in Virginia have a high likelihood not to break ground

For further insight into location siting, the row chart on the left provides a breakdown of Virginia counties and their average Project Completion Probability score (Figure 4). We can see that King William County in Virginia is the county with the highest average of projects likely to be completed at 33%. Within Virginia, we can also take a look at which developers in the state have the most success in bringing projects to completion. The row chart on the right provides a breakdown of the top fifteen developers in Virginia that have the most success in bringing projects to completion, with Open Road Renewables having the highest average project likelihood score, followed by NextEra Energy Resources (Figure 5). Armed with this data, developers can now more effectively evaluate the potential of competing planned projects coming online and plan their next project site accordingly.

counties-in-virginia-with-highest-average-project-score
Figure 4. Counties in Virginia with the highest average project probability score

For energy traders, project probability can also be used to compute the impact of proposed projects on congestion. In Panorama, after filtering out projects with a higher likelihood of completion (> 30%), in the area chart we can see the cumulative impact of these projects on the Etowanda to Hillside constraint over the next couple years. With this information, traders can make better assessments of where congestion may occur if a planned project does come online.

panorama-enverus-plants-table-and-system-map
Figure 6. Panorama Enverus Plants table and System Map

Conclusion

With the interconnection queue overwhelmed by the growing surge of renewable energy initiatives, it has made it increasingly difficult to identify viable projects. To successfully navigate the market, asset developers and traders must stay informed about each ISO’s power market dynamics and how generation mix can shift going forward. The Project Completion Probability score in the Project Tracking solution gives the ultimate advantage in navigating through queue uncertainties and complexities and help identify the projects most likely to reach commercial operation.

Interested in learning how Project Probability in the Project Tracking solution can help you identify which projects have a higher likelihood to be built? Reach out to our experts below and we will be glad to show you. 

Picture of Amanda De La Rosa

Amanda De La Rosa

Amanda De La Rosa is a Research Analyst on the Power and Renewables team at Enverus. She tracks power generation, transmission, and LMP data with a focus in the PJM market. Amanda holds a B.S. in Environmental Science & Policy from St. Edward’s University, and an M.Sc. in Biology from Ghent University.

Subscribe to the Enverus Blog

A weekly update on the latest “no-fluff” insight and analysis of the energy industry.

Related Content

Enverus Press Release - Looking past the CCUS power plant pipe dream
Analyst Takes Trading and Risk
ByAl Salazar, Enverus Intelligence® Research (EIR) Contributor
January 12, 2026

Unpack the Venezuela oil impact on Canadian energy as we analyze market shifts and the resilience of Canada's energy sector amid global changes.

Enverus/RatedPower Press Release - RatedPower publishes 2025 Global Renewable Trends Report examining the green landscape
Energy Market Wrap
ByEnverus
January 12, 2026

U.S. exits climate groups, Ascent leadership change, Kelt growth plans, Petrobras Búzios expansion, and Energy Transfer’s higher 2026 capital budget.

midstream-octg-thumbnail
Energy Transition
ByCarson Kearl, Enverus Intelligence® Research (EIR) Contributor
January 9, 2026

Aerospace-energy crossover Boom Technology, Inc. (trade name Boom Supersonic) is making waves beyond aviation with a recent deal to supply 29 Superpower 42 MW natural gas turbines, derived from its Symphony supersonic jet engine, to Crusoe. The AI infrastructure provider...

Enverus Intelligence® Research Press Release - Recap: How the Trump Administration is reshaping energy markets
Energy Transition
ByAshmal Dawoodani, Enverus Intelligence® Research
January 8, 2026

Our annual Global Energy Outlook highlights public infrastructure timelines continuing to lag the rapid pace of data center expansion, prompting hyperscalers to adopt behind-the-meter power solutions to accelerate availability. The outlook, published last month, summarizes our predictions on 2026 themes...

Enverus Press Release - Speed through records with Enverus Instant Analyst™ - Courthouse
Energy Transition
ByEnverus
December 30, 2025

As energy advisors and renewable energy consultants prepare for 2026, the power sector is entering a period of rapid transformation. With data center growth, electrification, and evolving policy landscapes driving unprecedented changes, your clients need actionable insights to make informed...

Enverus_Press_Release_Fundamental_Edge_1Q25_Thumbnail
Analyst Takes Trading and Risk
ByAl Salazar, Enverus Intelligence® Research (EIR) Contributor
December 22, 2025

Unlock real-time, actionable energy insights. This blog offers just a glimpse of the powerful analysis Oil & Gas Research delivers on today’s energy markets. Don’t miss the full picture. Click here to learn more. The energy landscape of 2025 has been...

Enverus Intelligence® Research Press Release - Surge in clean energy demand intensifies market competition
Trading and Risk
ByChris Griggs
December 17, 2025

If you trade natural gas, you already know the weather is your most volatile counterparty. A single arctic blast can send prices spiking, cut production via freeze-offs, and leave even seasoned desks exposed. Public models like the Global Forecast System...

Enverus Intelligence® Research Press Release - Winning in the West: Renewed opportunities are resurfacing in the DJ and PRB’s Niobrara
Energy Transition
ByAmyra Mardhani, Enverus Intelligence® | Research (EIR) Contributor
December 17, 2025

This week's ETT.

Enverus Press Release - Alternative fuels M&A focus turns from policy boosts to business resilience
Energy Market Wrap
ByEnverus
December 16, 2025

Top energy stories: Infinity buys Utica assets, Antero pivots to Marcellus, SM Energy plans $1B divestment, ExxonMobil and Chevron set bold growth targets.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Sign up for our Blog

Ready to Get Started?

Ready to Subscribe?

Register Today

Sign Up

Power Your Insights

Connect with an Expert

Access Product Tour

Speak to an Expert