PJM’s Large-Load Pipeline Is Running Ahead of Construction

byEnverus

Announcements have become a useful measure of where electricity demand may go, but they do not tell us when those loads will reach the grid. Enverus Intelligence® Research (EIR), using PRISM® Large Load Data, tracks capacity in three stages: operating, under construction and announced.

Across PJM, the October report lists 30.0 GW operating, 28.5 GW under construction and 113.6 GW announced. The reported total is 172.2 GW; the components differ by 0.1 GW because of rounding. Announced capacity is almost four times the amount under construction, a gap that makes timing central to the region’s demand outlook.

Virginia shows how wide the gap can be

Virginia has 44 GW of announced large-load capacity and 8 GW under construction, according to our datasets. That is a 5.5-to-1 difference. The announced figure is a pipeline indicator, while the construction figure describes projects that have moved further along. EIR says the gap raises questions about when announced projects may be realized and whether transmission capacity will be available.

The figures give planners and market participants a reason to look beyond headline demand totals. The pace of actual construction, energization and transmission work will determine how quickly a project pipeline becomes load on the system.

Selected PJM large-load capacity by status

PJM large-load capacity by status: operating, construction, announced
Source: Enverus Intelligence® Research, Quarterly New Build Power Resources Publication PJM, October 8, 2026.

Capacity shortfalls put the pipeline in focus

PJM’s two most recent Base Residual Auctions cleared below the region’s reliability requirement. EIR’s report cites shortfalls of about 6,517 MW for the 2027/28 delivery year and 6,831 MW for 2028/29. PJM proposed a Reliability Backstop Procurement to address the later shortfall. The original proposal described in the report included contracts of up to 15 years and a maximum willingness to pay of $555 per MW-day.

The schedule in the October 8 report has since changed. Following FERC’s September 29 order, PJM said it would not begin the procurement on September 30 as planned and would review the previously announced milestones. At the October 22 Members Committee meeting, PJM sought stakeholder input on revisions to its tariff filing. The early-December results date in the report reflects the original schedule.

What to watch next

The next signals are whether announced projects move into construction, how quickly projects already underway reach operation, and what transmission upgrades can support. EIR’s report provides a state-by-state view of large-load status alongside interactive maps and project tables for generation projects under construction and in pre-construction. Those details help readers compare what is being proposed with the projects moving through development.

For the state-by-state load view, interactive project maps and full project tables, explore the report.

About Enverus Intelligence® | Research, Inc. (EIR)

Enverus Intelligence® | Research, Inc. (EIR) is a subsidiary of Enverus that publishes energy-sector research focused on the oil, natural gas, power and renewable industries. EIR publishes reports including asset and company valuations, resource assessments, technical evaluations, and macroeconomic forecasts and helps make intelligent connections for energy industry participants, service companies, and capital providers worldwide. See additional disclosures here.

Picture of Enverus

Enverus

Energy’s most trusted SaaS platform — creating intelligent connections that uncover insights and opportunities to deliver extraordinary outcomes.

Subscribe to the Enverus Blog

A weekly update on the latest “no-fluff” insight and analysis of the energy industry.

Related Content
U.S. natural gas prices face power demand drag
Post
Power & Renewables, Power Trading
ByEnverus

ERCOT data shows large loads ramping at different rates as solar and battery additions keep pace, with new supply expected to slow in 2027.

Enverus Press Release - Prioritizing renewable PPA offtaker targets proves more challenging than expected
Post
Power & Renewables
ByThomas Popa

Senate’s bipartisan permitting bill data centers grid interconnection could curb speculative queues and speed transmission buildout.

Enverus Press Release - Renewable diesel: Too much of a good thing?
Post
Data Centers, Financial Services+1
  • Power & Renewables
ByEnverus

Validate data center natural gas supply: check pipeline capacity, contracts, routing, and long‑term durability before you commit.

Enverus Press Release - How much production growth can North America deliver over the next decade?
Post
Power & Renewables
ByEnverus

See how Enverus called ERCOT's August 2026 coincident peak a day early and pinpointed the exact peak hour, beating ERCOT's own load forecast accuracy.

Enverus Intelligence® Research Press Release - Recap: How the Trump Administration is reshaping energy markets
Post
Power & Renewables
ByEnverus

Learn how utilities, hyperscalers, and developers can score assets, align stakeholders, and structure power agreements that close faster and withstand scrutiny.

Enverus Intelligence® Research Press Release - Haynesville operators calculate remaining growth
Post
Power & Renewables
ByEnverus

Learn how utilities, hyperscalers, and developers can score assets, align stakeholders, and structure power agreements that close faster and withstand scrutiny.

Enverus Press Release - E&Ps with natural gas + CCS pave way for model data center development
Post
Power & Renewables
ByEnverus

MISO hit its $10,000/MWh cap on Sept. 2 as evening load surged, solar output collapsed, and imports weakened, triggering an EEA2 alert.

Enverus Intelligence® Research Press Release - Enhanced geothermal systems: The future of reliable, green power for AI data centers?
Post
Power & Renewables
ByEnverus

A $1 million-per-MW gap separates buying gas capacity from building it. See why utilities rarely run that comparison, and what it takes to defend the answer.

Enverus Press Release - Enverus Acquires BidOut, energy’s leading AI-powered procurement platform provider
Post
Power & Renewables
ByEnverus

Most FTR losses come from sound analysis with incomplete visibility. Learn the five pitfalls that separate winning desks from ones that explain away the losses.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Sign up for our Blog

Ready to Subscribe?

Ready to Get Started?