Interconnection Queue Decisions: Should I Stay or Should I Go?

byEnverus

In 1982, The Clash released “Should I Stay or Should I Go.” And while generator interconnection was unlikely their muse, the chorus does ring true for project developers navigating the interconnection process. 

Similar to the tenuous relationship in the song, the interconnection decision-making process is also non-transparent and wavering. On the one hand, developers want to “stay” in the queue but don’t want the costs to “double” (or more realistically, quadruple). On the other hand, they worry if they leave, “there will be trouble.” Though vastly simplified, this lyrical comparison does reflect that developers face much uncertainty in the interconnection process and struggle with answering “Should I Stay or Should I Go.” 

We promise not to spend this entire article drawing comparisons to a catchy 80’s hit. Rather, we will focus on how developers can add interconnection scenario analysis to their toolkits to help them bolster their interconnection queue decision analysis and provide more certainty on their projects’ interconnection fates. 

Time Is of the Essence for ISO Decision Point Analysis

As if interconnection wasn’t challenging enough, developers must make impactful decisions within short timelines imposed by transmission providers, otherwise known as ISO Decision Points (DPs). During these brief windows, developers perform interconnection queue decision analysis, digest study results, analyze and develop realistic scenarios, and complete financial analysis. If all of this diligence points to staying in the queue, developers then have to post a security deposit. And these security deposits are not nominal. For example, the average M2 security deposit for MISO DPP-21-South was $9.7 million, and Pearl Street estimates the average M2 deposit for DPP-22-South will be $8.5 million. 

So, how does a developer decide whether to stay or go? At Pearl Street, we encourage the practice of network upgrade cost scenario analysis—i.e., generate a cost range including a “floor” and a “ceiling.” 

To derive cost bookends, developers can run a variety of scenarios that usually fall within one of two categories: project-specific scenarios you can control or queue-related scenarios reflecting potential decisions made by other developers. We’ll dig into these categories in detail in the following sections. 

Project-Specific Scenarios You Can Control

When we say “project-specific,” we really mean scenarios that are under a developer’s control. In other words, these are changes to a developer’s project that are made independent of other projects. This potential set of scenarios is powerful because it gives a developer total autonomy with their project and lets them determine what upgrades they have the risk appetite to pay for. We’ve provided some project-specific scenarios below. 

  1. Project size reduction to mitigate an overload: In this scenario, a developer would determine the level of reduction needed to reduce a post-contingency loading to less than 100%. 
  1. Project size reduction to avoid cost allocation criteria: As an example, MISO and SPP outline criteria a project must meet to be cost-allocated, including meeting a minimum MW Impact. To reduce a project’s MW impact, a developer could choose to decrease the size of its project. For more information on MISO and SPP criteria, please refer to their respective study manuals. 
  1. Changes or reductions in service type: A developer could also reduce or remove its project’s NR/NRIS service type to avoid network resource-specific overloads. 

Queue-Related Scenarios Reflecting Potential Decisions Made by Others

In contrast to project-specific scenarios, queue-related scenarios are run to see how the variability of other projects in a cluster or prior cycle affects the cost allocation of a developer’s specific project. 

  1. Current cycle withdrawals: Historical interconnection queue withdrawal rates hover around 80%. Thus, a developer might want to run scenarios to determine what happens to its allocated cost when projects within its current cycle withdraw. Developers can simulate projects being withdrawn due to: 
    • High normalized cost ($/MW) by fuel type, transmission owner, state, county, etc. 
    • Strategic withdrawals based on geographic and/or electric proximity to a project 
    • Permitting info, renewables moratorium, and insight from RFPs.

  1. Prior queue withdrawals: Prior queue cycles can also have a direct impact on a developer’s interconnection costs and performing scenario analysis on previous study cycles is necessary as queues grow. One way in which developers can model these prior queue withdrawals is to determine which network upgrades could move from a previous cycle to the current one. Additionally, developers can identify breakpoints where system intact upgrades are no longer needed. Sidenote: this capability is unique to Interconnect™ subscribers. Instead of starting from a DISIS or DPP model and working backward, we start from scratch and build a new model for each scenario. 

Putting it All Together

Developers may want to run network upgrade cost scenario analysis for both project-specific and queue-related scenarios. And once they’ve conducted interconnection cost bookending, they still have to present these results and make a decision internally with information spanning departments. Interconnection engineers may like to use power flow results, project finance likely needs to model cost scenarios and to advance permitting/siting, the development team needs to know how likely a project is to move forward. 

Inside our developer-facing platform, Interconnect™, is a study scenario dashboard that highlights how estimated network upgrade costs change across any of the scenarios analyzed. Ultimately, this easy-to-digest format presents all relevant cost information in a way that each department can understand and utilize, thereby helping the team decide, “Should I stay or should I go.” 

Interconnect results

Conclusions

As much as we would like to offer a “magic bullet” for network upgrade costs, the nature of cluster studies prevents us from doing so. Pearl Street believes that analyzing multiple scenarios and viewing costs probabilistically, is the best way for developers to make a decision during a short timeline.  

Reach out to us to learn more about how Interconnect™ can help you optimize your MISO DPP and SPP DISIS cluster study scenario analyses. 

Picture of Enverus

Enverus

Energy’s most trusted SaaS platform — creating intelligent connections that uncover insights and opportunities to deliver extraordinary outcomes.

Subscribe to the Enverus Blog

A weekly update on the latest “no-fluff” insight and analysis of the energy industry.

Related Content

Enverus Intelligence® Research Press Release - Until LNG demand arrives, natural gas expected to struggle at $3
Energy Market Wrap
ByEnverus

Shell acquires ARC in a C$22B deal, Helix and Hornbeck merge, KKR exits Pembina Gas Infrastructure, Antero accelerates integration gains, and Golden Pass ships its first LNG cargo.

Enverus Press Release - Class VI wave expected to hit US
Energy Transition
ByBrynna Foley, Enverus Intelligence® Research

Rising solar PPA prices Shift Energy Economics Solar PPA prices climb as developers proceed with projects; Enverus details impacts on solar, wind, and storage markets.

Enverus Press Release - Welcome to EVOLVE 2025: Where visionaries converge to shape the future of energy
Energy Analytics Geoscience Analytics
ByEnverus

People have been calling the top of the Permian for years. And yet, they keep having to walk it back.  Our latest Permian inventory analysis from the Enverus Intelligence® Research (EIR) team shows why the basin continues to defy those...

Carbon storage in question: Illinois regulation could threaten key CCUS projects
Power and Renewables
ByMorgan Kwan

The S&P Global Commodities conference in Las Vegas brought together investors, developers, utilities, and hyperscalers at an inflection point for the power sector. Four themes dominated the conversation. Each one is directionally right. Each one is also commercially incomplete. Here’s...

Enverus Press Release - Decoding CCUS project success
Energy Transition
ByThomas Mulvihill

Discover how LG Energy and Samsung SDI are pivoting to grid energy storage as EV demand shifts and the BESS market expands.

Enverus Press Release - Looking past the CCUS power plant pipe dream
Energy Market Wrap
ByEnverus

This week’s Energy Market Wrap covers offshore consolidation, midstream dealmaking, rising gas demand from data centers and restored support for U.S. DAC hubs.

Shell strikes C$22 billion deal for Arc Resources
Analyst Takes Newsroom Topics
ByAndrew Dittmar

Shell’s $22 billion acquisition of Arc Resources vaults the supermajor into a leading Montney position and underscores Canada’s strategic importance in global LNG and integrated gas growth.

Enverus Press Release - Alternative fuels M&A focus turns from policy boosts to business resilience
Operators
ByIan Elchitz

Invoice-only AI can’t prevent pricing errors or budget surprises. Learn why AI in Source-to-Pay delivers better financial control through connected data and context.

U.S. oil and gas M&A slumps as low crude prices keep buyers in the dugout
Power and Renewables
ByEnverus

Power is now the primary constraint on data center development; not land, not capital, not compute. With grid interconnection queues stretching five to six years in key markets and ISOs acknowledging only about 20% of queued generation is actually under...

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Sign up for our Blog

Ready to Subscribe?

Ready to Get Started?

Ready to Subscribe?

Sign Up

Power Your Insights