Interconnection Queue Decisions: Should I Stay or Should I Go?

byEnverus

In 1982, The Clash released “Should I Stay or Should I Go.” And while generator interconnection was unlikely their muse, the chorus does ring true for project developers navigating the interconnection process. 

Similar to the tenuous relationship in the song, the interconnection decision-making process is also non-transparent and wavering. On the one hand, developers want to “stay” in the queue but don’t want the costs to “double” (or more realistically, quadruple). On the other hand, they worry if they leave, “there will be trouble.” Though vastly simplified, this lyrical comparison does reflect that developers face much uncertainty in the interconnection process and struggle with answering “Should I Stay or Should I Go.” 

We promise not to spend this entire article drawing comparisons to a catchy 80’s hit. Rather, we will focus on how developers can add interconnection scenario analysis to their toolkits to help them bolster their interconnection queue decision analysis and provide more certainty on their projects’ interconnection fates. 

Time Is of the Essence for ISO Decision Point Analysis

As if interconnection wasn’t challenging enough, developers must make impactful decisions within short timelines imposed by transmission providers, otherwise known as ISO Decision Points (DPs). During these brief windows, developers perform interconnection queue decision analysis, digest study results, analyze and develop realistic scenarios, and complete financial analysis. If all of this diligence points to staying in the queue, developers then have to post a security deposit. And these security deposits are not nominal. For example, the average M2 security deposit for MISO DPP-21-South was $9.7 million, and Pearl Street estimates the average M2 deposit for DPP-22-South will be $8.5 million. 

So, how does a developer decide whether to stay or go? At Pearl Street, we encourage the practice of network upgrade cost scenario analysis—i.e., generate a cost range including a “floor” and a “ceiling.” 

To derive cost bookends, developers can run a variety of scenarios that usually fall within one of two categories: project-specific scenarios you can control or queue-related scenarios reflecting potential decisions made by other developers. We’ll dig into these categories in detail in the following sections. 

Project-Specific Scenarios You Can Control

When we say “project-specific,” we really mean scenarios that are under a developer’s control. In other words, these are changes to a developer’s project that are made independent of other projects. This potential set of scenarios is powerful because it gives a developer total autonomy with their project and lets them determine what upgrades they have the risk appetite to pay for. We’ve provided some project-specific scenarios below. 

  1. Project size reduction to mitigate an overload: In this scenario, a developer would determine the level of reduction needed to reduce a post-contingency loading to less than 100%. 
  1. Project size reduction to avoid cost allocation criteria: As an example, MISO and SPP outline criteria a project must meet to be cost-allocated, including meeting a minimum MW Impact. To reduce a project’s MW impact, a developer could choose to decrease the size of its project. For more information on MISO and SPP criteria, please refer to their respective study manuals. 
  1. Changes or reductions in service type: A developer could also reduce or remove its project’s NR/NRIS service type to avoid network resource-specific overloads. 

Queue-Related Scenarios Reflecting Potential Decisions Made by Others

In contrast to project-specific scenarios, queue-related scenarios are run to see how the variability of other projects in a cluster or prior cycle affects the cost allocation of a developer’s specific project. 

  1. Current cycle withdrawals: Historical interconnection queue withdrawal rates hover around 80%. Thus, a developer might want to run scenarios to determine what happens to its allocated cost when projects within its current cycle withdraw. Developers can simulate projects being withdrawn due to: 
    • High normalized cost ($/MW) by fuel type, transmission owner, state, county, etc. 
    • Strategic withdrawals based on geographic and/or electric proximity to a project 
    • Permitting info, renewables moratorium, and insight from RFPs.

  1. Prior queue withdrawals: Prior queue cycles can also have a direct impact on a developer’s interconnection costs and performing scenario analysis on previous study cycles is necessary as queues grow. One way in which developers can model these prior queue withdrawals is to determine which network upgrades could move from a previous cycle to the current one. Additionally, developers can identify breakpoints where system intact upgrades are no longer needed. Sidenote: this capability is unique to Interconnect™ subscribers. Instead of starting from a DISIS or DPP model and working backward, we start from scratch and build a new model for each scenario. 

Putting it All Together

Developers may want to run network upgrade cost scenario analysis for both project-specific and queue-related scenarios. And once they’ve conducted interconnection cost bookending, they still have to present these results and make a decision internally with information spanning departments. Interconnection engineers may like to use power flow results, project finance likely needs to model cost scenarios and to advance permitting/siting, the development team needs to know how likely a project is to move forward. 

Inside our developer-facing platform, Interconnect™, is a study scenario dashboard that highlights how estimated network upgrade costs change across any of the scenarios analyzed. Ultimately, this easy-to-digest format presents all relevant cost information in a way that each department can understand and utilize, thereby helping the team decide, “Should I stay or should I go.” 

Interconnect results

Conclusions

As much as we would like to offer a “magic bullet” for network upgrade costs, the nature of cluster studies prevents us from doing so. Pearl Street believes that analyzing multiple scenarios and viewing costs probabilistically, is the best way for developers to make a decision during a short timeline.  

Reach out to us to learn more about how Interconnect™ can help you optimize your MISO DPP and SPP DISIS cluster study scenario analyses. 

Picture of Enverus

Enverus

Energy’s most trusted SaaS platform — creating intelligent connections that uncover insights and opportunities to deliver extraordinary outcomes.

Subscribe to the Enverus Blog

A weekly update on the latest “no-fluff” insight and analysis of the energy industry.

Related Content
U.S. natural gas prices face power demand drag
Post
Power & Renewables
ByThomas Popa

Senate’s bipartisan permitting bill data centers grid interconnection could curb speculative queues and speed transmission buildout.

Enverus Press Release - Enverus releases Investor Analytics: Refined, actionable financial insights at your fingertips
Post
Power & Renewables
ByAlex Nevokshonoff, Senior Analyst, Enverus Intelligence® | Research (EIR) Contributor

Reciprocating engine backlogs surge as developers favor modular gas-fired BTM solutions for faster time-to-power and shorter lead times.

Natural gas power M&A premiums double as data center demand and capital costs transform U.S. energy market
Post
Power & Renewables, Power Trading+1
  • Utilities
ByEnverus

EIR’s PJM and MISO winter outlook: a record El Niño, capped capacity auctions, MISO scarcity risk and heat rate forecasts for Dec. through Feb.

Aging-power-plant_1418205261-1
Post
Power & Renewables, Power Trading+1
  • Utilities
ByEnverus

EIR’s ISO-NE and NYISO winter outlook: how NECEC and CHPE reshape Northeast spreads, plus RGGI costs, El Niño weather and heat rate forecasts.

EIR’s model shows powered-land can rise more than 20-fold in value as data center sites reach energization
Post
Power & Renewables, Power Trading+1
  • Utilities
ByEnverus

EIR’s CAISO and Mid-C winter outlook: how a stormy El Niño, record battery activity, EDAM vs. Markets+ and carbon prices shape Western power.

Time-to-power gap Big generation’s Achilles’ heel in the AI data center race
Post
Power & Renewables, Power Trading
ByEnverus

PJM has 113.6 GW of announced large-load capacity, far more than the 28.5 GW under construction. See what the gap means for reliability and planning.

U.S. natural gas prices face power demand drag
Post
Power & Renewables, Power Trading
ByEnverus

ERCOT data shows large loads ramping at different rates as solar and battery additions keep pace, with new supply expected to slow in 2027.

Enverus Press Release - Prioritizing renewable PPA offtaker targets proves more challenging than expected
Post
Power & Renewables
ByThomas Popa

Senate’s bipartisan permitting bill data centers grid interconnection could curb speculative queues and speed transmission buildout.

Enverus Press Release - Renewable diesel: Too much of a good thing?
Post
Data Centers, Financial Services+1
  • Power & Renewables
ByEnverus

Validate data center natural gas supply: check pipeline capacity, contracts, routing, and long‑term durability before you commit.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Sign up for our Blog

Ready to Subscribe?

Ready to Get Started?