Interconnection Queue Decisions: Should I Stay or Should I Go?

byEnverus

In 1982, The Clash released “Should I Stay or Should I Go.” And while generator interconnection was unlikely their muse, the chorus does ring true for project developers navigating the interconnection process. 

Similar to the tenuous relationship in the song, the interconnection decision-making process is also non-transparent and wavering. On the one hand, developers want to “stay” in the queue but don’t want the costs to “double” (or more realistically, quadruple). On the other hand, they worry if they leave, “there will be trouble.” Though vastly simplified, this lyrical comparison does reflect that developers face much uncertainty in the interconnection process and struggle with answering “Should I Stay or Should I Go.” 

We promise not to spend this entire article drawing comparisons to a catchy 80’s hit. Rather, we will focus on how developers can add interconnection scenario analysis to their toolkits to help them bolster their interconnection queue decision analysis and provide more certainty on their projects’ interconnection fates. 

Time Is of the Essence for ISO Decision Point Analysis

As if interconnection wasn’t challenging enough, developers must make impactful decisions within short timelines imposed by transmission providers, otherwise known as ISO Decision Points (DPs). During these brief windows, developers perform interconnection queue decision analysis, digest study results, analyze and develop realistic scenarios, and complete financial analysis. If all of this diligence points to staying in the queue, developers then have to post a security deposit. And these security deposits are not nominal. For example, the average M2 security deposit for MISO DPP-21-South was $9.7 million, and Pearl Street estimates the average M2 deposit for DPP-22-South will be $8.5 million. 

So, how does a developer decide whether to stay or go? At Pearl Street, we encourage the practice of network upgrade cost scenario analysis—i.e., generate a cost range including a “floor” and a “ceiling.” 

To derive cost bookends, developers can run a variety of scenarios that usually fall within one of two categories: project-specific scenarios you can control or queue-related scenarios reflecting potential decisions made by other developers. We’ll dig into these categories in detail in the following sections. 

Project-Specific Scenarios You Can Control

When we say “project-specific,” we really mean scenarios that are under a developer’s control. In other words, these are changes to a developer’s project that are made independent of other projects. This potential set of scenarios is powerful because it gives a developer total autonomy with their project and lets them determine what upgrades they have the risk appetite to pay for. We’ve provided some project-specific scenarios below. 

  1. Project size reduction to mitigate an overload: In this scenario, a developer would determine the level of reduction needed to reduce a post-contingency loading to lessthan 100%. 
  1. Project size reduction to avoid cost allocation criteria: As an example, MISO and SPP outline criteria a project must meet to be cost-allocated, including meeting a minimum MW Impact. To reduce a project’s MW impact, a developer could choose to decrease the size of its project. For more information on MISO and SPP criteria, please refer to their respective study manuals. 
  1. Changes or reductions in service type: A developer could also reduce or remove its project’s NR/NRIS service type to avoid network resource-specific overloads. 

Queue-Related Scenarios Reflecting Potential Decisions Made by Others

In contrast to project-specific scenarios, queue-related scenarios are run to see how the variability of other projects in a cluster or prior cycle affects the cost allocation of a developer’s specific project. 

  1. Current cycle withdrawals: Historical interconnection queue withdrawal rates hover around 80%. Thus, a developer might want to run scenarios to determine what happens to its allocated cost when projects within its current cycle withdraw. Developers can simulate projects being withdrawn due to: 
    • High normalized cost ($/MW) by fuel type, transmission owner, state, county, etc. 
    • Strategic withdrawals based on geographic and/or electric proximity to a project 
    • Permitting info, renewables moratorium, and insight from RFPs.

  1. Prior queue withdrawals: Prior queue cycles can also have a direct impact on a developer’s interconnection costs and performing scenario analysis on previous study cycles is necessary as queues grow. One way in which developers can model these prior queue withdrawals is to determine which network upgrades could move from a previous cycle to the current one. Additionally, developers can identify breakpoints where system intact upgrades are no longer needed. Sidenote: this capability is unique to Interconnect™ subscribers. Instead of starting from a DISIS or DPP model and working backward, we start from scratch and build a new model for each scenario. 

Putting it All Together

Developers may want to run network upgrade cost scenario analysis for both project-specific and queue-related scenarios. And once they’ve conducted interconnection cost bookending, they still have to present these results and make a decision internally with information spanning departments. Interconnection engineers may like to use power flow results, project finance likely needs to model cost scenarios and to advance permitting/siting, the development team needs to know how likely a project is to move forward. 

Inside our developer-facing platform, Interconnect™, is a study scenario dashboard that highlights how estimated network upgrade costs change across any of the scenarios analyzed. Ultimately, this easy-to-digest format presents all relevant cost information in a way that each department can understand and utilize, thereby helping the team decide, “Should I stay or should I go.” 

Interconnect results

Conclusions

As much as we would like to offer a “magic bullet” for network upgrade costs, the nature of cluster studies prevents us from doing so. Pearl Street believes that analyzing multiple scenarios and viewing costs probabilistically, is the best way for developers to make a decision during a short timeline.  

Reach out to us to learn more about how Interconnect™ can help you optimize your MISO DPP and SPP DISIS cluster study scenario analyses. 

Picture of Enverus

Enverus

Energy’s most trusted SaaS platform — creating intelligent connections that uncover insights and opportunities to deliver extraordinary outcomes.

Subscribe to the Enverus Blog

A weekly update on the latest “no-fluff” insight and analysis of the energy industry.

Related Content
data-center-demand
Post
Power & Renewables
ByEnverus

Virginia's new data center tax and Dominion's GS-5 rate class reveal who really pays for load growth, and which cost-allocation tool actually holds up.

Enverus Intelligence® Research Press Release - Enhanced geothermal systems: The future of reliable, green power for AI data centers?
Post
Power & Renewables
ByBrynna Foley, Enverus Intelligence® Research

GEV's gas turbine backlog hits 116 GW, delaying deliveries to 2031 and reshaping build-vs-buy in power markets.

Enverus Press Release - Enverus releases inaugural Top US Drillers and customer rankings
Post
Trading & Risk
ByAlex Nevokshonoff, Senior Analyst, Enverus Intelligence® | Research (EIR) Contributor

Pipeline delay stalls Oracle's Project Jupiter, threatening Bloom Energy fuel cells powering the Stargate data center.

Enverus Intelligence® Research Press Release - Surge in clean energy demand intensifies market competition
Post
Energy Analytics, Operators
ByEnverus

Developers and investors can't compare gas, solar, and storage using separate models. Here's what a standardized cross-asset framework actually requires.

Enverus Press Release - Enverus honored as one of Alberta’s leading employers
Post
Financial Services
ByColton Wright

FERC's 2026 interconnection reforms are reshaping large-load project finance. Here's what five key changes mean for energy investors and project bankability.

Enverus Press Release - Speed through records with Enverus Instant Analyst™ - Courthouse
Post
Power & Renewables
ByEnverus

See how Enverus day-ahead solar forecasts outperformed ISO forecasts in ERCOT and CAISO during May–June 2026, including the June heat wave events.

Enverus Media Advisory - Trump vs. Harris: A tale of two energy policies
Post
Minerals
ByEnverus

Global energy demand, infrastructure constraints and commodity trends are reshaping mineral markets. Watch the Enverus 2026 outlook webinar replay.

Enverus Press Release - No pain, no gain: Short-term headwinds for natural gas could bring beneficial long-term tailwinds
Post
Operators
BySimon Goettl

Horseshoe wells are unlocking stranded Eagle Ford acreage, cutting drilling costs 15% by solving lease geometry constraints that blocked development plans.

data-center-demand
Post
Power & Renewables
ByThomas Mulvihill

ChargePoint and Optimus expand EV fast charging infrastructure across the Southeast, adding 200+ public fast chargers to retail and QSR sites.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Sign up for our Blog

Ready to Subscribe?

Ready to Get Started?