Energy Analytics Power & Renewables

Queued Up | Shifting Ground for Large Loads 

byCarson Kearl, Enverus Intelligence® Research (EIR) Contributor

Enverus Intelligence® Research (EIR) estimates an average load growth of about 12 GW in PJM by 2035, driven primarily by data center load expansion. PJM’s independent market monitor filed a complaint arguing the grid operator has clear authority to delay interconnection of large new data centers until sufficient generation and transmission are available. The filing follows stalled stakeholder talks on new large-load rules and warns unchecked data center growth is inflating transmission costs and driving billions in higher capacity prices. The monitor is urging the Federal Energy Regulatory Commission to quickly clarify PJM’s authority as the board prepares its own interconnection proposal.

A recent EIR report analyzed 94 large-load tariffs from 36 utilities and determined large loads that bring their own generation can better flex demand during peak hours and benefit from rate structures tied to those highs. They can reduce demand during peak hours by participating in demand response programs or using an optimized battery storage strategy.

The experience in AEP Ohio, where speculative requests fell by more than half after a new rate was introduced, suggests tariff design itself can ease pressure on load-connection queues (Figure 1). Similarly, SPP’s High Impact Large Load process and Alberta’s proposed Bill 8 aim to prioritize or accelerate interconnection for those providing their own generation, demonstrating how policy and pricing signals can streamline the addition of major new loads.

Research Highlights: 

  • Distributed Generation | The Turbines Are Coming – This report challenges the general belief in the market that power-generating equipment, namely large turbines, is limiting near-term data center growth.
  • Utility Rate Refocus | Reliable Cost Recovery – This report analyzes 94 electrical tariffs across leading cloud markets to better understand how utilities recover capital from large-scale customers and manage the surge in high-demand interconnection requests.
  • Geothermal Acreage | Hot Rocks and High Bids – This report examines the tenfold rise in geothermal lease prices in the western U.S., driven increasingly by transmission access and data center proximity rather than subsurface traits.

The Public Utility Regulatory Policies Act was enacted in 1978 to promote competition and energy efficiency by requiring utilities to buy power from qualifying facilities at rates based on the avoided cost of generating that power.

About Enverus Intelligence® | Research, Inc. (EIR)

Enverus Intelligence® | Research, Inc. (EIR) is a subsidiary of Enverus that publishes energy-sector research focused on the oil, natural gas, power and renewable industries. EIR publishes reports including asset and company valuations, resource assessments, technical evaluations, and macroeconomic forecasts and helps make intelligent connections for energy industry participants, service companies, and capital providers worldwide. See additional disclosures here.

Picture of Carson Kearl, Enverus Intelligence® Research (EIR) Contributor

Carson Kearl, Enverus Intelligence® Research (EIR) Contributor

As an analyst on the Enverus Intelligence® Research (EIR) team, Carson is the lead on data centers and advanced energy technologies. He was previously an analyst on the macro team and has additional experience advising large industrial consumers on their energy consumption. His education in economics at the University of Alberta focused on industrial organization and power markets.

Subscribe to the Enverus Blog

A weekly update on the latest “no-fluff” insight and analysis of the energy industry.

Related Content
Enverus Press Release - Enverus Earns Top Workplaces Honors for Fourth Consecutive Year
Post
Power & Renewables
ByEnverus

MISO's August 2026 outlook: softer peaks vs. July, forecast converging with the market, and new Gulf Coast gas capacity reshaping South flows.

Enverus Press Release - No pain, no gain: Short-term headwinds for natural gas could bring beneficial long-term tailwinds
Post
Operators
BySimon Goettl

Manual lease review breaks down at scale, and buried obligations don't surface until it's too late. See how operators are closing that gap.

Enverus Intelligence® Research Press Release - Enhanced geothermal systems: The future of reliable, green power for AI data centers?
Post
Power & Renewables
ByEnverus

ERCOT's August 2026 risk hinges on baked-in heat, 80 GW peak scenarios, and CP exhaustion. See what could keep prices high despite a cheaper supply stack.

Enverus Press Release - Enverus honored as one of Alberta’s leading employers
Post
Trading & Risk
ByChris Griggs

Why diesel crack spread hits $100: refining outages, not crude, driving record diesel prices and pump pain.

Enverus Press Release - Decoding CCUS project success
Post
Trading & Risk
ByAlex Nevokshonoff, Senior Analyst, Enverus Intelligence® | Research (EIR) Contributor

Explore Enverus forecasts: behind-the-meter generation growth to 2030, modular gas and fuel cells outpacing large CCGTs for data centers.

Enverus Press Release - Data center demand and quantifying the exponential levers needed to power them
Post
ByIan Elchitz

Alberta oil sands producers waiting for $100 oil while weighing CCUS costs, pipeline choices and market volatility.

Enverus Press Release - Enverus Acquires BidOut, energy’s leading AI-powered procurement platform provider
Post
Trading & Risk
ByAl Salazar, Enverus Intelligence® Research (EIR) Contributor

Alberta oil sands producers waiting for $100 oil while weighing CCUS costs, pipeline choices and market volatility.

Enverus Press Release - Enverus releases Investor Analytics: Refined, actionable financial insights at your fingertips
Post
Power & Renewables
ByCarson Kearl, Enverus Intelligence® Research (EIR) Contributor

Texas data center moratorium targets audits on tax breaks and community impact; ready projects continue through Batch Zero.

data-center-demand
Post
Power & Renewables
ByEnverus

Virginia's new data center tax and Dominion's GS-5 rate class reveal who really pays for load growth, and which cost-allocation tool actually holds up.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Sign up for our Blog

Ready to Subscribe?

Ready to Get Started?