Power and Renewables

Find High-Capacity POIs Fast With ATC Data in Enverus PRISM®

How to Spot High-Potential Substations Using Planning Models and Historical Available Transfer Capacity (ATC)

byRobin Grathwohl
June 26, 2025

Are you struggling to find substations with real injection potential? In this blog, you’ll learn how developers use planning models and historical ATC data in PRISM to identify viable POIs, avoid costly surprises in the queue and confidently move forward with high-potential projects.

First off, what is available transfer capacity (ATC)?

ATC refers to the remaining power transfer capability from a particular substation to the transmission network. It represents the maximum amount of power that can be transmitted over a transmission line without compromising grid reliability and stability.

Why is ATC important for power project and large load developers?

With the increasing demand for electric power and the integration of renewable energy into the U.S. power market, the process of adding new power to the grid and navigating interconnection has become more complex. Historically, fossil fuel plants have been built in centralized locations, simplifying interconnection to the grid. However, an influx of renewables as well as large load centers in the U.S. power market is resulting in a decentralized grid, creating a more complex interconnection process.

How does ATC impact injection studies during the interconnection process?

The rapid growth of renewable development has created a competitive landscape for developers seeking ideal project sites and interconnection points. During the lengthy study process to reach project interconnection, developers may incur significant costs to complete the process. To mitigate study costs, developers now seek ways to assess their projects’ impact on the grid early in the site selection process. Understanding the available capacity of substations within the grid is crucial for this purpose.

How can Enverus Power & Renewables ATC solutions help you with your injection study?

Enverus Power & Renewables offers ATC solutions to help developers screen for substations with available capacity early in the project siting process. Using the PRISM application, developers can track both planning case ATC values and historical state estimator ATC values from the ISO at the substation level to identify substations with feasible injection capabilities for their future power plants.

What is a planning case?

A planning case is a forward-looking model used by grid operators and planners to simulate future grid conditions under various scenarios. It incorporates assumptions about load growth, generation additions, retirements and transmission upgrades to evaluate how the power system might perform in a specific future year and season. These models help identify potential constraints, assess system reliability and guide infrastructure investment decisions. For developers, planning cases offer critical insights into where future injection capacity may exist, helping to inform site selection and project feasibility.

What is State Estimator ATC?

State Estimator (ATC) is a real-time or near-real-time measure of how much additional power can be transferred through the grid without violating operational limits. Derived from actual system conditions using state estimation tools, it reflects the dynamic nature of the grid, including current flows, outages and system constraints. Unlike planning cases, which are based on forecasts, State Estimator ATC provides a snapshot of the grid’s current flexibility. For developers, this data can reveal historical trends and operational bottlenecks, offering a practical perspective on how substations have performed over time.

Let’s take a look and see all this in action in PRISM

Figure 1: In PRISM, this widget depicts injection capability in MW by bus in Texas based on the High Peak Load Summer 2031 planning case via the PRISM platform. We can see these data points from specific regions, ISOs and across North America.

In ERCOT’s planning models, multiple scenarios across different seasons and year timeframes are built to assess future changes in the grid. Knowing how the ISO will judge projects in the interconnection process is crucial for developers who are attempting to find the least costly solutions to building projects.

To start the screening process across all of Texas to find a potential point of interconnection (POI) with the capacity to support new projects, developers will focus on the worst-case scenario which is likely the High Peak Load Summer five to six years out. Figure 1 depicts the expected injection capacity across all 345kv+ buses in ERCOT in a high peak load scenario in the summer of 2031.

Figure 2: This bubble chart from PRISM shows the mean of injection capability (MW) compared to the total planned capacity in each county in TX via the High Peak Load Summer 2031 planning case. This data is pre-filtered to all injection capabilities above 100 MWs.

The ERCOT planning models include a multitude of assumptions about the future state of the grid including the assumption that all power plants with an interconnection agreement in ERCOT will be operational by the given timeframe. Developers know that there is a lot ahead of them in the queue, which includes many projects that will reach commercial operations, and a few that will successfully provide power to the grid. In assessing the planning case outputs, it’s necessary to also consider, outside of just the projects in an Interconnection Agreement stage, what other capacity is planned at a point of interest. Figure 2 compares the Injection Capability in MWs to the total planned capacity by county in this high peak load summer 2031 planning model. Counties like Tom Green and Scurry may show relatively high injection capability values, but the amount of capacity ahead in the queue may deter a developer from considering these areas for future interconnection.

Figure 3: PRISM compares modeled injection values across two 345kV substations in Reeves and Sutton Counties, using all potential cases from the ERCOT 2025 planning models. Enverus customers are expected to interconnect at POIs averaging over 500 MW of available injection capacity.

There are two 345 kV substations located in Reeves and Sutton counties that, according to the Summer 2031 peak load planning model, each have over 1,000 MW of potential injection capacity. However, both currently have less than 400 MW of total planned capacity. This suggests that these substations could support large-scale solar or wind projects, especially given the relatively low capacity already ahead of them in the interconnection queue.

While the ISO is likely to evaluate projects based on worst-case scenarios, it’s also important to consider the full range of potential capacity at each substation across different planning models. If a substation is overloaded in any scenario, it indicates that certain grid conditions could prevent additional injection without requiring significant grid upgrades.

Figure 3 illustrates the variation in injection capacity across all modeled scenarios in the ERCOT 2025 planning model. For example, Orsted shows a relatively narrow range of injection values across scenarios, whereas the Riverton substation exhibits a much wider range from approximately 1,300 MW to more than 5,000 MW, highlighting the variability and potential uncertainty in available capacity.

Figure 4: PRISM provides a time series of historical ATC, in megawatts, for the Orsted and Riverton substations—enabling users to identify transmission trends, evaluate siting decisions and better assess project feasibility based on real operational data.

Given the variability in potential injection capacity across different planning scenarios, developers may also want to examine historical trends at these substations. By leveraging the Historical (ATC) data available through PRISM, users can analyze the monthly average injection capacity over the past two years. This historical perspective can provide valuable context for understanding how each substation has performed under real-world conditions.

Figure 4 illustrates the injection capability over time for each substation, offering insight into seasonal patterns, consistency and potential constraints.

Figure 5: PRISM visualizes transmission infrastructure, including planned lines around the Riverton substation that are incorporated into ERCOT’s planning models; only Enverus provides this level of visibility into transmission infrastructure helping users anticipate future grid enhancements and evaluate potential interconnection opportunities.

Interestingly, the historical injection capacity at both the Orsted and Riverton substations has been lower than the ranges projected in the planning models. Figure 5 highlights the actual routes of planned transmission lines, as digitized by the Enverus GIS team, which ERCOT has identified in its most recent planning model. While historical data may reflect limited injection capability, the addition of these new transmission lines is expected to enhance capacity in this region, potentially unlocking greater injection potential soon.

With a clearer understanding of the modeled injection capacity at key substations, developers can begin evaluating other critical project siting factors, such as land suitability, to advance their development plans. The modeled capacity provides confidence in exploring areas near the Riverton and Orsted substations for potential projects.

Focusing on a 1-mile radius around the Riverton substation, Figure 6 illustrates the total MWac of solar power that could be generated across all parcels within that area. This estimate is based on PRISM’s buildable acreage calculations, integrated with RatedPower’s design tools to model expected power output. The analysis suggests that this area could potentially generate nearly 685 MWac of solar power positioned near a substation modeled to support more than 1,000 MW of injection capacity even under worst-case grid conditions projected for 2031.

Figure 6: Enverus Power & Renewables, parcels 1-mile around the Riverton substation colored by their Rated Power MWac, which is a modelled output of the potential solar power that can be built on the land. On the right is a summation of that MW ac value across all substations in the area as well as a sum of the total buildable acreage given Enverus PRISM’s least restrictive buildable analysis view. Enverus customers found land that was 20% more buildable than non-Enverus customers.

Ultimately, developers need to understand the available capacity to interconnect to the grid prior to other steps in their project siting process to ensure successful interconnection and reduce injection study costs and potential upgrade costs further down the line. PRISM assists developers in quickly finding substations with available capacity per ISO planning models and historical state estimator values, and subsequently the land to support projects around those sites.

About Enverus Power & Renewables

Enverus is the largest energy-only focused software company in the world. More than 6,000 businesses use our solutions, including more than 1,000 in electric power markets. Every day, 7,500+ users utilize our solutions to develop and design projects, manage the grid, trade power, and buy and sell assets.

Our differentiation stems from the fact that not all data and platforms are created equal. We collect and connect thousands of disparate, disorganized data sets to provide the most comprehensive analytics-ready data on power markets. We have a 25-year head start on the market and have made more than $200 million of acquisitions focused on power. We collect more data, cover more projects and provide value across more of the asset lifecycle than any competitor. We have invested more than $3 billion in our platform so we can deliver it all in the most modern and capable software platform custom built for energy.

Picture of Robin Grathwohl

Robin Grathwohl

Robin Grathwohl is a product owner for Enverus, having joined the company in 2021. With a diverse background in utility and biology research, she brings a unique perspective to her role, leveraging her BA in environmental science and education from Colorado College to drive innovation. Her passion for environmental conservation fuels her commitment to supporting the development of cutting-edge software solutions for power and renewables.

Subscribe to the Enverus Blog

A weekly update on the latest “no-fluff” insight and analysis of the energy industry.

Related Content

Enverus Intelligence Research Press Release - Upstream M&A sails to $17 billion in 1Q25
Business Automation Energy Analytics
ByEnverus
November 10, 2025

Current Market Snapshot Crude prices have softened, and the ripple effects are clear: U.S. oil and gas M&A activity has slowed dramatically as buyers hesitate to commit capital in an uncertain environment. For small and mid-sized operators, this caution translates...

Enverus Press Release - Heightened natural gas price volatility expected amid supply and demand challenges
Energy Market Wrap
ByEnverus
November 7, 2025

Explore this week's top energy stories—from M&A to renewables and infrastructure shifts. Stay informed with Enverus.

Enverus Press Release - Welcome to EVOLVE 2025: Where visionaries converge to shape the future of energy
Analyst Takes Trading and Risk
ByAl Salazar, Enverus Intelligence® Research (EIR) Contributor
November 7, 2025

The current oil market forecast indicates significant oversupply to come as roughly 2.9 billion barrels of crude and petroleum products are stored in OECD tanks today, up from the typical total of 2.7-2.8 billion. At Enverus Intelligence® Research (EIR), our...

Enverus Press Release - Enverus reveals Texas’ renewable energy hot shots
Energy Transition
ByAdam Robinson, Enverus Intelligence® | Research (EIR) Contributor
November 6, 2025

Our latest research shows interconnection queues across major independent system operators have swelled with speculative requests from landowners betting on the AI boom, driving up utility timelines and pushing developers away.

Enverus Intelligence® Research Press Release - OPEC+ cuts and Trump tariffs force price downgrade
Energy Analytics
ByEnverus
November 5, 2025

A Market in Hibernation The U.S. oil and gas M&A market is eerily quiet. Many public buyers are focused on digesting recent acquisitions or avoiding assets that could dilute their portfolios. Private equity firms, despite sitting on dry powder, are...

Enverus Press Release - Updated US residential solar and storage forecast predicts major shifts in power demand by 2050
Power and Renewables
ByEnverus
November 4, 2025

The summer 4CP season is in the books—and for power traders and asset managers, every coincident peak counts. Miss the signal, and you’re paying someone else’s peak. Catch it early, and you protect margin.  Enverus nailed every single one.  Utilizing...

Enverus Intelligence® Research Press Release - Lower oil prices could lead to Permian spending cuts
Energy Market Wrap
ByEnverus
November 4, 2025

This week’s energy headlines spotlight emerging gas plays, rapid integration wins, midstream expansions, offshore momentum and capital market innovation. Here are five stories that stood out:  Also this week: Momentum Midstream’s NG3 pipeline goes live, Amplify Energy exits East Texas,...

SM Merges with Civitas as public E&P consolidation picks up
Analyst Takes News Release
ByAndrew Dittmar
November 3, 2025

In response to today's announcement that SM Energy and Civitas Resources have agreed to merge into a single company with an enterprise value of $12.8 billion, based on prior-day closing prices and including net debt, Andrew Dittmar, principal analyst at...

Enverus Press Release - Upstream M&A sails on with $30 billion in 2Q24
Energy Analytics Operators
ByEnverus
October 31, 2025

Strategies for Maximizing Asset Value and Staying Ahead in a Maturing Market Why Inventory Pressure Matters Now Top-tier drilling locations are becoming scarce, and oil and gas operators are feeling the squeeze. The need to redevelop mature assets and extract...

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Sign up for our Blog

Register Today

Sign Up

Power Your Insights

Connect with an Expert

Access Product Tour

Speak to an Expert