The Queue Before the Queue | GEV’s Backlog Extends to 2031

byBrynna Foley, Enverus Intelligence® Research

GEV’s gas turbine backlog climbed to 116 GW in Q2, up from 100 GW in the prior quarter as utilities, independent power producers (IPPs) and data center developers continue securing generation equipment years in advance. Turbine demand has intensified to the point that the supplier is now sold out until 2031 for deliveries.

The growing backlog strengthens the position of existing gas-fired generation. Equipment lead times are one element of drastic increases in new build CCGT costs, up more than 2x since 2020. It is becoming increasingly difficult to build new CCGTs. In ERCOT’s current market, a highly efficient CCGT requires a PPA of ~$70/MWh to achieve bankable returns, while the same asset in PJM requires a capacity price upwards of $400/MW-day.

This trend is also reflected in secondary markets who have seen similar levels of inflation in the price paid for operational assets, which continue to transact at approximately ½ that of replacement costs (Figure 1). The build-vs-buy dilemma remains tilted toward acquisitions. For companies seeking exposure to near-term load growth, purchasing existing generation remains the more attractive path.

This blog offers just a glimpse of the powerful analysis Power and Energy Transition Research delivers on the trending themes. Don’t miss the full picture.

Research Highlights:

The company has an installed base of over 7,000 gas turbines and around 55,000 wind turbines, which together produce about 25% of the world’s electricity.

Top Three Takeaways:

1: How large is GEV’s gas turbine backlog, and when are deliveries available?

GEV’s gas turbine backlog climbed to 116 GW in Q2, up from 100 GW in the prior quarter. Demand from utilities, independent power producers (IPPs) and data center developers has intensified to the point that the supplier is now sold out until 2031 for deliveries.

2: Why is building a new CCGT so difficult today?

New CCGT costs have risen more than 2x since 2020, with equipment lead times a key driver of that inflation. In ERCOT’s current market, a highly efficient CCGT requires a PPA of approximately $70/MWh to achieve bankable returns, while the same asset in PJM requires a capacity price upwards of $400/MW-day.

3: Why does the build-vs-buy dilemma favor acquiring existing gas assets?

Operational assets continue to transact at approximately half of replacement costs. With new CCGT economics strained by supply chain constraints and rising prices, purchasing existing generation remains the more attractive path for companies seeking exposure to near-term load growth.

About Enverus Intelligence® | Research, Inc. (EIR)

Enverus Intelligence® | Research, Inc. (EIR) is a subsidiary of Enverus that publishes energy-sector research focused on the oil, natural gas, power and renewable industries. EIR publishes reports including asset and company valuations, resource assessments, technical evaluations, and macroeconomic forecasts and helps make intelligent connections for energy industry participants, service companies, and capital providers worldwide. See additional disclosures here.

Picture of Brynna Foley, Enverus Intelligence® Research

Brynna Foley, Enverus Intelligence® Research

Brynna Foley joined the Enverus Intelligence® Research team as a Power & Renewables Analyst in October 2024, focusing on Power Assets. She holds a degree in Electrical Engineering from Queen’s University and brings two years of industry experience in engineering design and corporate strategy. With a solid foundation in electrical systems and market analysis, Brynna is passionate about leveraging data analytics to drive the energy transition.

Subscribe to the Enverus Blog

A weekly update on the latest “no-fluff” insight and analysis of the energy industry.

Related Content
Enverus Press Release - Enverus releases Investor Analytics: Refined, actionable financial insights at your fingertips
Post
Power & Renewables
ByAlex Nevokshonoff, Senior Analyst, Enverus Intelligence® | Research (EIR) Contributor

Reciprocating engine backlogs surge as developers favor modular gas-fired BTM solutions for faster time-to-power and shorter lead times.

Natural gas power M&A premiums double as data center demand and capital costs transform U.S. energy market
Post
Power & Renewables, Power Trading+1
  • Utilities
ByEnverus

EIR’s PJM and MISO winter outlook: a record El Niño, capped capacity auctions, MISO scarcity risk and heat rate forecasts for Dec. through Feb.

Aging-power-plant_1418205261-1
Post
Power & Renewables, Power Trading+1
  • Utilities
ByEnverus

EIR’s ISO-NE and NYISO winter outlook: how NECEC and CHPE reshape Northeast spreads, plus RGGI costs, El Niño weather and heat rate forecasts.

EIR’s model shows powered-land can rise more than 20-fold in value as data center sites reach energization
Post
Power & Renewables, Power Trading+1
  • Utilities
ByEnverus

EIR’s CAISO and Mid-C winter outlook: how a stormy El Niño, record battery activity, EDAM vs. Markets+ and carbon prices shape Western power.

Time-to-power gap Big generation’s Achilles’ heel in the AI data center race
Post
Power & Renewables, Power Trading
ByEnverus

PJM has 113.6 GW of announced large-load capacity, far more than the 28.5 GW under construction. See what the gap means for reliability and planning.

U.S. natural gas prices face power demand drag
Post
Power & Renewables, Power Trading
ByEnverus

ERCOT data shows large loads ramping at different rates as solar and battery additions keep pace, with new supply expected to slow in 2027.

Enverus Press Release - Prioritizing renewable PPA offtaker targets proves more challenging than expected
Post
Power & Renewables
ByThomas Popa

Senate’s bipartisan permitting bill data centers grid interconnection could curb speculative queues and speed transmission buildout.

Enverus Press Release - Renewable diesel: Too much of a good thing?
Post
Data Centers, Financial Services+1
  • Power & Renewables
ByEnverus

Validate data center natural gas supply: check pipeline capacity, contracts, routing, and long‑term durability before you commit.

Enverus Press Release - How much production growth can North America deliver over the next decade?
Post
Power & Renewables
ByEnverus

See how Enverus called ERCOT's August 2026 coincident peak a day early and pinpointed the exact peak hour, beating ERCOT's own load forecast accuracy.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Sign up for our Blog

Ready to Subscribe?

Ready to Get Started?