Clearing the Queue | Senate Unveils Bipartisan Permitting Bill

byThomas Popa

Large data centers would have to shoulder their full grid costs and back projects with financial assurances under a bipartisan permitting bill introduced Sept. 30. The Bipartisan American Affordability and Jobs Act applies those requirements to facilities of 20 MW or more. It also narrows National Environmental Policy Act reviews and would allow the Federal Energy Regulatory Commission (FERC) to permit interstate transmission lines after a year of state inaction. The Senate is targeting a procedural vote Nov. 9.

Enverus Intelligence® Research has flagged two bottlenecks the bill seeks to address: speculative load clogging interconnection queues and transmission lagging behind load growth. As interconnection timelines lengthen, more developers are turning to behind-the-meter (BTM) generation. Our latest forecast projects nearly 35% of data center capacity will be served by BTM resources by 2035 (Figure 1).

Transmission constraints are showing up as congestion premiums in parts of ERCOT and PJM. The bill takes on both. Its financial-assurance requirement resembles AEP Ohio’s 2025 data center tariff, which cut the utility’s data center queue by about half. By discouraging speculative interconnection requests and accelerating transmission development, the legislation could make grid service more attractive relative to BTM alternatives. FERC backstop siting authority could also speed permitting for interstate transmission projects that help reduce congestion premiums.

The outcome of the Nov. 9 vote remains uncertain, but the shift the bill seeks to address is already reflected in our forecast, which tracks announced grid-fed and BTM data center capacity across every major U.S. power market through 2035.

This blog offers just a glimpse of the powerful analysis Power and Energy Transition Research delivers on the trending themes. Don’t miss the full picture.

Research Highlights:

Pattern Energy’s 550-mile SunZia transmission line, which runs from central New Mexico to south-central Arizona, took about 17 years to permit and roughly 2.5 years to build. Its initial federal environmental review took seven years, more than triple the two-year deadline proposed under the bipartisan Senate permitting bill.

Top Three Takeaways:

1: What is driving the shift toward behind-the-meter generation for data centers?

As interconnection timelines lengthen, more developers are turning to BTM generation. Enverus Intelligence® Research projects nearly 35% of data center capacity will be served by BTM resources by 2035.

2: What does the bipartisan permitting bill require of large data centers?

Facilities of 20 MW or more would have to pay their full grid costs and back projects with financial assurances. The bill also narrows National Environmental Policy Act reviews and would allow FERC to permit interstate transmission lines after a year of state inaction.

3: How could the bill affect transmission congestion in ERCOT and PJM?

Transmission constraints are showing up as congestion premiums in parts of ERCOT and PJM, and the bill targets both speculative queue requests and transmission delays. Its financial-assurance requirement resembles AEP Ohio’s 2025 data center tariff, which cut the utility’s data center queue by about half.

Upcoming Events

About Enverus Intelligence® | Research, Inc. (EIR)

Enverus Intelligence® | Research, Inc. (EIR) is a subsidiary of Enverus that publishes energy-sector research focused on the oil, natural gas, power and renewable industries. EIR publishes reports including asset and company valuations, resource assessments, technical evaluations, and macroeconomic forecasts and helps make intelligent connections for energy industry participants, service companies, and capital providers worldwide. See additional disclosures here.

Picture of Thomas Popa

Thomas Popa

Thomas Popa joined the Enverus Intelligence® Research team as an associate on the AI Infrastructure team in May 2026, focusing on data center and neocloud economics and the valuation of large-load infrastructure. Thomas holds a degree in Mathematics and Economics from the University of British Columbia. With a solid foundation in quantitative modeling and economic analysis, Thomas is passionate about using data to explain how AI-driven load growth is reshaping the power sector.

Subscribe to the Enverus Blog

A weekly update on the latest “no-fluff” insight and analysis of the energy industry.

Related Content
Enverus Press Release - Renewable diesel: Too much of a good thing?
Post
Data Centers, Financial Services+1
  • Power & Renewables
ByEnverus

Validate data center natural gas supply: check pipeline capacity, contracts, routing, and long‑term durability before you commit.

Enverus Press Release - How much production growth can North America deliver over the next decade?
Post
Power & Renewables
ByEnverus

See how Enverus called ERCOT's August 2026 coincident peak a day early and pinpointed the exact peak hour, beating ERCOT's own load forecast accuracy.

Enverus Intelligence® Research Press Release - Recap: How the Trump Administration is reshaping energy markets
Post
Power & Renewables
ByEnverus

Learn how utilities, hyperscalers, and developers can score assets, align stakeholders, and structure power agreements that close faster and withstand scrutiny.

Enverus Intelligence® Research Press Release - Haynesville operators calculate remaining growth
Post
Power & Renewables
ByEnverus

Learn how utilities, hyperscalers, and developers can score assets, align stakeholders, and structure power agreements that close faster and withstand scrutiny.

Enverus Press Release - E&Ps with natural gas + CCS pave way for model data center development
Post
Power & Renewables
ByEnverus

MISO hit its $10,000/MWh cap on Sept. 2 as evening load surged, solar output collapsed, and imports weakened, triggering an EEA2 alert.

Enverus Intelligence® Research Press Release - Enhanced geothermal systems: The future of reliable, green power for AI data centers?
Post
Power & Renewables
ByEnverus

A $1 million-per-MW gap separates buying gas capacity from building it. See why utilities rarely run that comparison, and what it takes to defend the answer.

Enverus Press Release - Enverus Acquires BidOut, energy’s leading AI-powered procurement platform provider
Post
Power & Renewables
ByEnverus

Most FTR losses come from sound analysis with incomplete visibility. Learn the five pitfalls that separate winning desks from ones that explain away the losses.

Enverus Intelligence® Research Press Release - Until LNG demand arrives, natural gas expected to struggle at $3
Post
Power & Renewables
ByEnverus

Enverus identified the ERCOT July 2026 coincident peak one day in advance. See how our day-ahead forecasts outperformed ERCOT during a critical summer heat wave.

Enverus Press Release - CO2 pipeline economics: The missing link
Post
Power & Renewables
ByEnverus

PJM's August 2026 base case sits above market on heat rate, with RGGI costs and capacity risk keeping the stack tight even as transmission relief arrives.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Sign up for our Blog

Ready to Subscribe?

Ready to Get Started?