Power and Renewables

Uncover prime renewable project sites in MISO with planned transmission lines and customizable buildable acres 

byEvan Powell
January 18, 2024

Renewables are a necessity to counter growing power demand and support decarbonization, but however, finding the least costly and most viable location for renewable assets is becoming increasingly challenging. In Midcontinent Independent System Operator (MISO), more than 240,000 MW of proposed solar and wind projects have been withdrawn within the past five years, the most for all independent system operators (ISO) in the United States (Figure 1). Developers in MISO are faced with high upgrade costs resulting from congestion in the grid, an inability to find locations where the solar and wind resources can support their projects, and a struggle to find suitable land for projects. By evaluating planned transmission lines along with solar and wind yields and buildable acres, developers can overcome many of these challenges and find prime renewable project sites at lower upgrade costs and achieve higher returns that are not obvious at first glance. 

project-capacity
Figure 1: A breakdown of the suspended project capacity (MW) in each ISO queue over the past five years.

Evaluate planned transmission to find sites with lower upgrade costs

To counter the challenge of grid upgrade costs within MISO, developers can consider sites near planned transmission lines as feasible points of interconnection when siting projects. These planned or under construction transmission lines will likely soon have the available capacity to support interconnection, helping relieve the potential upgrade costs associated with connecting to the grid.

This map from Enverus PRISM® (Figure 2) displays where planned transmission lines are located within the MISO region. Planned lines are any lines that have the status of “Pre-Construction”, “Under Construction” or “Built – Not in Operation”. The bulk of the new builds in MISO are in Illinois (Figures 2 and 3).

It is pertinent to note that proposed transmission lines will often contain multiple potential routes that are being considered in the planning process. Thus, projects in the “Pre-Construction” phase will typically include some route possibilities that never come to fruition. By the time construction starts these routes will be narrowed down to just the chosen locations.

Figure 2: Map of planned transmission lines within MISO territory
Figure 3: Top five states in MISO territory by miles of planned transmission lines

Finding the highest solar and wind yields to maximize returns

Based on the prevalence of planned lines within the state, Illinois could be a promising location for project development. However, the presence of new-build transmission lines is not enough to ensure that a solar or wind asset will succeed. Beyond the transmission infrastructure present, developers must also consider the prevalence of solar or wind resources that would ensure the highest yield for their plant.

For solar assets, global horizontal irradiance (GHI) is a valuable measure of the total solar radiation on a horizontal surface. It is used to estimate expected PV panel output. Figure 5 shows a map of Illinois with both the average daily solar GHI and all planned transmission lines overlaid on top. It is optimal to site solar projects in areas with higher GHI values.

Figure 5: Map of Illinois with planned transmission lines and average daily solar GHI values

A solar developer would likely focus on the southern portion of Illinois, where average daily GHI values are generally higher than the remainder of the state, in turn resulting in more effective solar plants.

The Mt Vernon Area Reliability Project (ENV Transmission ID 146487) is the largest planned line within this region of Southern Illinois, where daily GHI values are consistently higher. It is currently in pre-construction and is owned by Ameren Illinois, one of the largest transmission owners in the MISO. It stretches across both Jefferson and Wayne counties, Illinois – two of the top five counties in the state by planned transmission line miles. And when complete, it will consist of two segments: a Mt. Vernon-Reifen substation route (projected to be complete by the end of 2025) and a Reifen-Kays substation route (projected to be complete by the end of 2026). Each of these segments currently has seven possible proposed routes, but eventually only one route from each segment will be built.

Finding sites with buildable acres

After identifying potential areas with favorable solar and wind yield and a high likelihood planned transmission lines will be built nearby, developers can start to narrow down their search to the parcel level and find sites that would be suitable to build their next renewable project. Figure 6 shows a map of all parcels within three miles of at least one of the possible transmission line routes, sorted by their percentage of buildable acreage. Parcels color-coded green have over 95% buildable acreage, while red parcels have less than 95% buildable acreage.

Figure 6: Map of parcels within three miles of any Mt Vernon Area Reliability Project proposed transmission lines, colored by their buildable acreage (%)

Developers can leverage these parcels surrounding the Mt. Vernon Area Reliability Project (Figure 6) as ideal sites that have the potential for successful solar assets. However, this introduces the next challenge for a developer looking to site solar in MISO. How does one narrow down their search to land that is viable to build on?

The ability to assess buildability at scale is critical. In Figure 6, all parcels within three miles of at least one of the possible transmission line routes have been color-coded by the percentage of buildable acreage available. Green parcels have a buildable acreage percentage over 95%, meaning that less than 5% of its land area contains excessive slope, canopy, floodplains or wetlands. This feature can be utilized to highlight the parcels that are most viable for building solar plants.

Two parcels that fit this criterion particularly well are highlighted in Figures 7 and 8.

Figure 7: Map of the Mt Vernon Area Reliability Project proposed transmission lines, with other power plants and nearby parcels of interest highlighted.
Figure 8: Closeup of the selected parcels of interest.

When dealing with transmission projects that still have multiple route options available, it is important to keep in mind that only one route per segment will ultimately be chosen. For this reason, users will want to look for parcels that are located nearby as many of the route options as possible. In doing so, they are prepared with potential project sites near whichever route is eventually chosen.

These parcels fit that requirement well- they are directly adjacent to seven of the eight possible routes for the Reifen-Kays segment of the project (Routes I-N), so there is a high likelihood that they will be in prime position for easy interconnection access to those lines. Both parcels also have a buildable acreage percentage well over 95%, so there is lots of room to build a project.

Once a developer finds land that is buildable, they then need to assess where within that plot of land they could site their project, as well as potential hinderances to development. Each developer has different criteria for land they consider buildable. In PRISM, the Customizable Buildable Acreage model includes the ability to manipulate these settings to conform to a developer’s specific needs (see Figure 9 ).

Figure 9: Sample Customizable Buildable Acreage model settings. This includes all layers users can include  in their analysis, specifications for slope and canopy limits, and the ability to apply custom setbacks on every layer. Users can run this model on parcels of interest to assess buildability.

Figure 10 shows a map of those parcels with the customizable buildable acreage tool applied and the settings as shown in Figure 9. This feature allows developers to get a far more detailed understanding of the parcel’s actual layout. While the buildable acreage % can be useful for quickly ruling out parcels that would be difficult to build on, siting a project requires getting a sense of where exactly the hazards are to understand how the land can be used to complete a project.


In Figure 10, we see the result of applying the CBA model settings from Figure 9 . The default setback selected in this example is 10 feet, meaning any hazards on the map also extend out 10 feet in all directions, except slope and canopy whose setbacks were slightly different. Building directly next to heavy canopy, roads or wetlands, for example, will often not be feasible, so the model includes setbacks to show where panels could be placed on the parcel. However, this is highly customizable. If a developer were in a situation where they were required to leave 20 feet between panels and roads, for example, they could easily make that change.


Also, the Slope and Canopy settings allow users to customize the severity of those hazards they want to account for. In this example, slopes greater than 5% and canopy densities greater than 80% were set as cutoffs. Developers who are willing to build on more extreme slopes though, for example, or who only want to deal with very sparse tree canopies, can easily make those changes within the tool.

This allows developers to get a much more detailed view of where exactly on the parcel they can and cannot build, and the exact obstacles in the way. In these parcels (Figure 10), for example, the western half of the lot appears clear to build on, but the eastern half contains some wetlands, canopy and high-slope areas that will need to be worked around.

Figure 10: Parcels of interest with Customizable Buildable Acreage tool applied. The green areas are considered buildable based on model inputs. The other colors represent a specific hinderance to development.

Leveraging the planned transmission line dataset allows developers to site projects in places where available transfer capacity will be high and grid upgrade costs will be low. In conjunction with tools like the solar GHI feature, the parcels buildable acreage %, and the Customizable Buildable Acreage Model, developers can quickly evaluate large swaths of parcels to find suitable sites for renewable projects.  With the use of these PRISM tools and datasets, users can discover prime sites that others may have overlooked if they had not performed an in-depth analysis on the planned transmission lines, solar and wind yields, and buildable acres.

Picture of Evan Powell

Evan Powell

Evan Powell joined Enverus in 2020 as a research analyst on the Power and Renewables team. His focus areas include tracking power generation, transmission and LMP data within the CAISO region and integrating the Energy Information Administration (EIA) and utility queues data into Enverus PRISM®. He graduated from the Colorado School of Mines with a Bachelor’s degree in Mechanical Engineering and a Master’s in Engineering and Technology Management.

Subscribe to the Enverus Blog

A weekly update on the latest “no-fluff” insight and analysis of the energy industry.

Related Content

Enverus and Pexapark Press Release - Enverus Enhances Global Trading & Risk Platform with Pexapark’s Benchmark Renewables Pricing and Market Intelligence
Energy Transition
ByCarson Kearl, Enverus Intelligence® Research (EIR) Contributor
December 3, 2025

Enverus Intelligence® Research (EIR) estimates an average load growth of about 12 GW in PJM by 2035, driven primarily by data center load expansion. PJM’s independent market monitor filed a complaint arguing the grid operator has clear authority to delay...

Enverus Press Release - Enverus releases “2025 Interconnection Queue Outlook” to navigate backlogged grid challenges
Power and Renewables
ByEnverus
December 2, 2025

October in ERCOT brought a mix of seasonal challenges—unusually warm temperatures early in the month, a sharp cooldown later, and notable variability in renewable generation. These conditions tested the accuracy of short-term and day-ahead forecasts, which are essential for power...

Enverus Press Release - Enverus honored as one of Alberta’s leading employers
Energy Analytics Operators
ByAlexandra Castaneda
December 1, 2025

Uncover hidden insights for Canadian heavy oil multilateral wells. Enverus PRISM provides comprehensive data to benchmark, evaluate designs, and identify emerging strategies like fishbone wells.

Enverus Intelligence® Research Press Release - Delayed data center demand response: How quickly can ISOs add new loads?
Business Automation
ByEnverus
November 28, 2025

Field ticketing is the backbone of service validation and payment in upstream oil and gas operations—but for many operators, it’s also a source of daily headaches. From paperwork overload to payment delays and coding disputes, the challenges are real and...

Enverus Press Release - The Denver Post names Enverus a Top Workplace in Colorado
Analyst Takes Trading and Risk
ByAl Salazar, Enverus Intelligence® Research (EIR) Contributor
November 24, 2025

Unlock insights into Canada's energy potential. Analyze policy shifts, pipeline development, and LNG Canada's role in meeting global energy demand.

Enverus Intelligence® Research Press Release - Wood you believe it? BECCS is taking off and creating overlooked, lucrative opportunities
Energy Market Wrap
ByEnverus
November 21, 2025

DT Midstream expands Haynesville, Texas gains CCS primacy, BOEM plans offshore lease sale, and Chevron boosts Permian recovery—get the full energy update.

Enverus Intelligence® Research Press Release - Waha prices expected to go negative (again)
Energy Transition
ByAshmal Dawoodani, Enverus Intelligence® Research
November 20, 2025

Blackstone announced last week it will invest about $1.2 billion to build the Wolf Summit Energy Project in West Virginia as forecast load growth in the region continues to drive demand for baseload generation. In contrast to earlier announcements of...

Enverus/RatedPower Press Release - RatedPower publishes 2025 Global Renewable Trends Report examining the green landscape
Energy Market Wrap
ByEnverus
November 14, 2025

Top energy stories: Baytex exits U.S., Chevron’s growth plan, Harvest LNG deal, Energy Transfer records, and Baker Hughes LNG order.

Enverus Press Release - Modeling EPA’s new Subpart W revision and the super-emitter wild card
Energy Analytics Geoscience Analytics
BySarah Peters Lancaster
November 14, 2025

Inventory scarcity is no longer a distant concern; it’s here, and it’s reshaping upstream strategies. As Tier 1 inventory dwindles and energy demand rises, operators face mounting pressure to discover, extend and optimize resources in increasingly complex environments. The subsurface...

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Sign up for our Blog

Register Today

Sign Up

Power Your Insights

Connect with an Expert

Access Product Tour

Speak to an Expert