China’s Order No. 837 adds project-delay risk to U.S. power supply chains

New approval requirements for engineering, training and remote support could add uncertainty to active U.S. power projects

byJon Haubert

CALGARY, Alberta (Sep. 2, 2026) — Enverus Intelligence® Research (EIR), a subsidiary of Enverus, the leading energy data analytics platform, is releasing a report that finds China’s new outbound investment framework could add a new source of project-delay risk for U.S. power developers that rely on Chinese-linked engineering, training, remote technical guidance and other ongoing support.

While existing U.S. measures remain the primary barriers to Chinese participation in the power supply chain, Order No. 837 adds potential approval requirements to certain ongoing service relationships, making recurring technical support more exposed than equipment purchases.

Battery storage and solar inverters face the greatest incremental exposure, according to EIR, because active Chinese-linked service relationships remain in place. Existing U.S. measures, including Prohibited Foreign Entity restrictions, Section 301 tariffs and Uyghur Forced Labor Prevention Act enforcement, remain the primary structural barriers to Chinese participation.

For U.S. developers, the added risk is potential disruption or delay to existing supplier relationships as companies assess how to comply with requirements on cross-border technical support.

“Order No. 837 does not fundamentally change the barriers already limiting Chinese participation in the U.S. power supply chain, but it introduces another point of uncertainty for projects that depend on ongoing technical support. The practical risk is that engineering, training and other recurring services could face approval requirements that create delays or disrupt existing operating arrangements,” said Heather Leahey, principal analyst at EIR.

Key takeaways:

  • China’s Order No. 837 took effect July 1 and establishes a dedicated outbound investment framework covering Chinese entities investing abroad or transferring technologies to foreign recipients.
  • The regulation focuses on continuing knowledge, personnel and data flows, including certain engineering, training and remote technical-support relationships.
  • Battery storage and solar inverters are identified as having high incremental disruption risk under Order No. 837.
  • Existing U.S. policy remains the more durable structural barrier to Chinese participation, while Order No. 837 adds potential Chinese-side approval risk to certain service relationships.

EIR’s analysis pulls from a variety of products including Enverus ONE™.

You must be an Enverus Intelligence® Research subscriber to access this report.

Full copies of EIR research reports cannot be distributed to members of the media. Journalists interested in learning more about this analysis are encouraged to use our Request Media Interview button to schedule a time to meet with one of our expert analysts, who can provide context, insight, and deeper discussion of the findings.

About Enverus Intelligence® Research
Enverus Intelligence ® | Research, Inc. (EIR) is a subsidiary of Enverus that publishes energy-sector research focused on the oil, natural gas, power and renewable industries. EIR publishes reports including asset and company valuations, resource assessments, technical evaluations and macro-economic forecasts; and helps make intelligent connections for energy industry participants, service companies and capital providers worldwide. Enverus is the most trusted, energy-dedicated SaaS company, with a platform built to create value from generative AI, offering real-time access to analytics, insights and benchmark cost and revenue data sourced from our partnerships to 95% of U.S. energy producers, and more than 40,000 suppliers. Learn more at Enverus.com.

Picture of Jon Haubert

Jon Haubert

Jon Haubert is the communications director at Enverus. Members of the media should use our Request Media Interview option on the Enverus Newsroom page to schedule an interview with one of our expert analysts.

Related News

Enverus ONE™ delivers new AI capabilities, turning complex questions into power market decision-ready insights
Newsroom
Power & Renewables
ByJon Haubert

Enverus is expanding Power Analyst across PRISM®, Mosaic, Panorama and RatedPower, bringing energy-focused AI into more customer workflows to help teams turn complex questions into decision-ready insights faster.

Strathcona merges with Greenfire for up to C$2.9 Billion
Newsroom
Analyst Takes, Financial Services+1
  • Operators
ByMichael Berger

Strathcona Resources’ C$2.7 billion-C$2.9 billion merger with Greenfire Resources creates a ~160,000 bbl/d oil sands pure-play and significantly expands its undeveloped SAGD inventory. Enverus Intelligence Research examines the valuation, strategic rationale and why oil sands M&A may cool from here.

Solar PPA prices need 49% average increase to offset tax credit loss
Newsroom
Financial Services, Power & Renewables
ByJon Haubert

Enverus Intelligence® Research finds solar PPA prices must rise 49% on average to preserve modeled project returns without the federal investment tax credit.

U.S. upstream M&A reached $12.6 billion in 3Q26 before accelerating with another $18 billion in October. Enverus Intelligence® Research examines the trends driving dealmaking, from emerging Permian intervals and Eagle Ford redevelopment to growing international demand for U.S. natural gas.
Newsroom
Financial Services, Operators
ByJon Haubert

U.S. upstream M&A reached $12.6 billion in 3Q26 before accelerating with another $18 billion in October. Enverus Intelligence® Research examines the trends driving dealmaking, from emerging Permian intervals and Eagle Ford redevelopment to growing international demand for U.S. natural gas.

EQT Builds an Appalachian Super Producer with $13.8B Range Buy
Newsroom
Analyst Takes, Financial Services+1
  • Operators
ByAndrew Dittmar

EQT’s nearly $14 billion acquisition of Range Resources creates America’s largest natural gas producer, combining scale, premium inventory and infrastructure to compete in an increasingly complex North American gas market.

EIR’s model shows powered-land can rise more than 20-fold in value as data center sites reach energization
Newsroom
Financial Services, Power & Renewables
ByJon Haubert

Explore Enverus Intelligence® Research’s six-stage powered-land valuation framework, including how utility power commitments and development risks shape site value as projects advance toward energization.

Transmission upgrade timelines vary more than 3x across owners
Newsroom
Financial Services, Power & Renewables
ByJon Haubert

Enverus Intelligence® Research finds transmission upgrade timelines vary more than threefold by owner across four U.S. power markets, highlighting delivery risks for large-load projects.

U.S. power grid set for 1,080 GW generation expansion by 2050
Newsroom
Financial Services, Renewable Developers
ByJon Haubert

Enverus Intelligence® Research projects 1,080 GW of new U.S. power capacity through 2050, led by 376 GW of battery storage as grid reliability shapes the energy mix.

Established operators lead ERCOT large-load queue
Newsroom
Financial Services, Power & Renewables
ByJon Haubert

Enverus Intelligence® Research finds that 81% of identified hyperscaler capacity is classified as ERCOT base-load, compared with 31% for new entrants, highlighting differences in transmission readiness.

Find Out How Enverus Can Help Your Business
Subscribe to the Energy Blog

A weekly update on the latest “no-fluff” insight and analysis of the energy industry.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Get Started

Sign up for our Blog

Ready to Subscribe?

Ready to Get Started?