CALGARY, Alberta (Oct. 20, 2026) — Enverus Intelligence® Research (EIR), a subsidiary of Enverus, the leading energy data analytics platform, is releasing new research examining how project maturity and operating history relate to large-load classifications in Texas’ ERCOT power market.
The report finds that 81% of identified hyperscaler capacity falls within ERCOT’s base-load classification, compared with just 31% for new entrants. The findings suggest that operating history, construction progress and interconnection evidence are more closely associated with transmission-path certainty than sponsor type alone.
ERCOT’s Batch Zero process conditionally classified 204 projects totaling 66.4 GW as base-load and 158 projects totaling 125.4 GW as studied load. Base-load projects have a more established transmission path, while studied-load projects face additional transmission studies that may introduce upgrade requirements, cost exposure and energization delays. Neither classification guarantees energization.
EIR’s analysis also highlights the challenges facing newer developers. New entrants represent 18.5 GW across 44 identified campuses, including 12.7 GW classified as studied load. Across named projects, studied-load campuses average 576 MW, compared with 393 MW for base-load campuses, underscoring the scale of projects facing additional transmission requirements.
“The distinction emerging from ERCOT’s Batch Zero process is less about who is developing the project and more about how far that project has progressed. Established operators generally have more evidence of operating history and development readiness, while newer projects face additional transmission studies that could affect their energization timelines,” said Juan Arteaga, PhD, report author and principal analyst at EIR.
Key takeaways:
- Established hyperscalers have greater base-load exposure: 81% of identified hyperscaler capacity is classified as base-load, compared with 31% for new entrants.
- New entrants face additional transmission requirements: Of the 18.5 GW represented by new entrants across 44 campuses, 12.7 GW is classified as studied load.
- Larger projects face less-defined energization paths: Named studied-load campuses average 576 MW, compared with 393 MW for base-load campuses.
- Operating history distinguishes project readiness: Of the identified base-load capacity, 46% is already energized, compared with none of the identified studied-load capacity.
- Classification does not guarantee energization: ERCOT’s conditional designations indicate transmission-path certainty rather than overall commercial viability.
EIR’s analysis pulls from a variety of products including Enverus ONE™.
You must be an Enverus Intelligence® Research subscriber to access this report.
Full copies of EIR research reports cannot be distributed to members of the media. Journalists interested in learning more about this analysis are encouraged to use the Request Media Interview button to schedule a time to meet with one of our expert analysts, who can provide context, insight, and deeper discussion of the findings.
About Enverus Intelligence® Research
Enverus Intelligence ® | Research, Inc. (EIR) is a subsidiary of Enverus that publishes energy-sector research focused on the oil, natural gas, power and renewable industries. EIR publishes reports including asset and company valuations, resource assessments, technical evaluations and macro-economic forecasts; and helps make intelligent connections for energy industry participants, service companies and capital providers worldwide. Enverus is the most trusted, energy-dedicated SaaS company, with a platform built to create value from generative AI, offering real-time access to analytics, insights and benchmark cost and revenue data sourced from our partnerships to 95% of U.S. energy producers, and more than 40,000 suppliers. Learn more at Enverus.com.