Transmission upgrade timelines vary more than 3x across owners

Study of four U.S. power markets highlights delivery risks for large-load projects

byJon Haubert

CALGARY, Alberta (Oct. 27, 2026) — Enverus Intelligence® Research (EIR), a subsidiary of Enverus, the leading energy data analytics platform, is revealing significant differences in transmission upgrade timelines across major U.S. power markets, with median construction times varying more than threefold depending on the transmission owner. The findings underscore a critical consideration for large-load developers: where a project connects to the grid — and who owns the transmission infrastructure — can substantially influence how long it takes to deliver power.

EIR’s analysis finds that median transmission upgrade construction timelines range from 12.3 months for Company A to 42.6 months for Company B, exposing substantial differences that regional market averages can obscure. Based on 5,901 completed transmission upgrades and a constraint study covering 47,488 interconnection points across ERCOT, MISO, PJM and SPP, the findings identify transmission owner execution, capital cycles and regulatory posture as important contributors to project delivery timelines.

The research also highlights the potential for significant schedule overruns relative to median construction timelines. Across the four markets, 90th-percentile (P90) transmission upgrade durations range from 53.8 to 61.9 months. For developers planning major new electricity loads, these findings demonstrate why evaluating owner-specific construction histories alongside regional market conditions is important when assessing power delivery risk.

“Our analysis shows that selecting a power market is only part of the equation for large-load developers. Transmission owners operating under the same regional processes can have substantially different construction timelines. Understanding those differences is important when evaluating how quickly a project can receive power,” said Carson Kearl, senior analyst and report author at EIR.

Key takeaways:

  • Transmission owner selection matters: Median upgrade construction timelines vary more than threefold across transmission owners, ranging from 12.3 months at Company A to 42.6 months at Company B.
  • Regional market averages can conceal delivery differences: Owner execution, capital cycles and regulatory posture contribute to substantial variation in construction timelines, including among owners operating within the same regional planning processes.
  • Long-tail construction risks persist: P90 transmission upgrade durations range from 53.8 to 61.9 months across ERCOT, MISO, PJM and SPP, substantially exceeding median construction timelines.
  • Large electricity loads frequently require upgrades: At 500 MW, 85%–94% of interconnection points across the four markets require network upgrades.
  • Extensive historical analysis supports the findings: EIR assessed 5,901 completed transmission upgrades alongside constraint data covering 47,488 interconnection points across four major power markets.

EIR’s analysis pulls from a variety of products including Enverus ONE.

You must be an Enverus Intelligence® Research subscriber to access this report.

EIR research reports cannot be distributed to members of the media without a scheduled interview. Journalists interested in learning more about this analysis are encouraged to request a media interview with one of our expert analysts, who can provide context, insight, and deeper discussion of the findings.

About Enverus Intelligence® Research
Enverus Intelligence ® | Research, Inc. (EIR) is a subsidiary of Enverus that publishes energy-sector research focused on the oil, natural gas, power and renewable industries. EIR publishes reports including asset and company valuations, resource assessments, technical evaluations and macro-economic forecasts; and helps make intelligent connections for energy industry participants, service companies and capital providers worldwide. Enverus is the most trusted, energy-dedicated SaaS company, with a platform built to create value from generative AI, offering real-time access to analytics, insights and benchmark cost and revenue data sourced from our partnerships to 95% of U.S. energy producers, and more than 40,000 suppliers. Learn more at Enverus.com.

Picture of Jon Haubert

Jon Haubert

Jon Haubert is the communications director at Enverus. Members of the media should use our Request Media Interview option on the Enverus Newsroom page to schedule an interview with one of our expert analysts.

Related News

U.S. power grid set for 1,080 GW generation expansion by 2050
Newsroom
Financial Services, Renewable Developers
ByJon Haubert

Enverus Intelligence® Research projects 1,080 GW of new U.S. power capacity through 2050, led by 376 GW of battery storage as grid reliability shapes the energy mix.

Established operators lead ERCOT large-load queue
Newsroom
Financial Services, Power & Renewables
ByJon Haubert

Enverus Intelligence® Research finds that 81% of identified hyperscaler capacity is classified as ERCOT base-load, compared with 31% for new entrants, highlighting differences in transmission readiness.

Anadarko Basin offers leading economics as inventory expands
Newsroom
Financial Services, Operators
ByJon Haubert

Enverus Intelligence® Research finds the Anadarko Basin leads major Lower 48 plays on full-cycle economics at $60/bbl, with expanding inventory, growing private-operator participation and production expected to rise through 2030.

Oil sands M&A returns with Cenovus’ Athabasca purchase
Newsroom
Analyst Takes, Financial Services+1
  • Operators
ByMichael Berger

Cenovus Energy's acquisition of Athabasca Oil marks a major oil sands M&A transaction. Analysis from Enverus Intelligence® Research highlights rising asset valuations, limited acquisition targets and the growing premium placed on long-life Canadian oil sands resource.

Barnett-Woodford holds largest undeveloped oil resource in the Midland Basin
Newsroom
Financial Services, Operators
ByJon Haubert

Enverus Intelligence® Research identifies the Midland Barnett-Woodford as the Lower 48’s largest oil-directed expansion opportunity, with more than 6,400 locations and approximately 3 Bbbl of undeveloped recoverable oil resource.

Montney liquids scarcity grows as Canadian natural gas supply expands
Newsroom
Financial Services, Operators
ByJon Haubert

Enverus Intelligence® Research estimates high-liquids regions hold about 30 years of inventory versus roughly 90 years in lean-gas areas as associated supply adds pressure to AECO.

Appalachia Ample resource beyond depleting cores
Newsroom
Financial Services, Operators
ByJon Haubert

Enverus Intelligence® Research examines how maturing Marcellus and Utica core inventory is being offset by adjacent fairways, new delineation and deeper resource across Appalachia.

U.S. gas supply growth could outpace LNG demand through 2027
Newsroom
Financial Services, Operators
ByJon Haubert

Enverus Intelligence® Research lowers its 2027 Henry Hub forecast to $3.25/MMBtu as accelerating Haynesville production and Permian gas expansion outpace near-term LNG demand growth.

Aging U.S. shale elevates Canada’s role in North American energy supply
Newsroom
Financial Services, Operators
ByJon Haubert

Enverus Intelligence® Research finds U.S. oil production is likely to peak in the early 2030s as low-cost inventory tightens, increasing the importance of Canada’s deeper resource base to North American supply.

Find Out How Enverus Can Help Your Business
Subscribe to the Energy Blog

A weekly update on the latest “no-fluff” insight and analysis of the energy industry.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Get Started

Sign up for our Blog

Ready to Subscribe?

Ready to Get Started?