News Release

Off the grid, on the gas

EIR predicts 62 GW of new data center capacity in Lower 48 through 2030 as grid constraints increase reliance on behind-the-meter generation

byJon Haubert

CALGARY, Alberta (July 21, 2026) — Enverus Intelligence® Research (EIR), a subsidiary of Enverus, has released a new report examining how hyperscaler capital spending could translate into new data center capacity and greater use of dedicated natural gas generation.

EIR forecasts approximately 62 GW of new Lower 48 data center capacity additions through 2030, supported by roughly $5 trillion in cumulative hyperscaler capital expenditures from 2026 through 2030. The buildout is expected to be concentrated in PJM, ERCOT, MISO and WECC, which together account for more than 80% of forecast capacity additions through 2030.

Grid interconnection congestion and long development timelines are also pushing a growing share of capacity toward behind-the-meter generation. EIR estimates that behind-the-meter projects will account for roughly 40% of installed capacity and imply approximately 1.3 Bcf/d of incremental natural gas demand by 2030, with about half concentrated in ERCOT and PJM.

Near-term project visibility remains comparatively strong, with approximately 96% of forecast 2028 additions tied to projects under construction or in late-stage development. That share falls to 26% by 2030, reflecting greater uncertainty around unannounced, uncontracted and outer-year projects.

“Data center growth is increasingly reliant on behind-the-meter infrastructure. Our forecast indicates that grid interconnection constraints will shape not only where capacity is built, but also how it is powered, with behind-the-meter natural gas generation emerging as a primary path for projects that cannot wait for traditional grid access,” said Carson Kearl, report author and associate at EIR.

Key takeaways:

  • EIR estimates approximately 62 GW of new Lower 48 data center capacity additions through 2030.
  • PJM, ERCOT, MISO and WECC are expected to absorb more than 80% of new capacity through 2030.
  • Behind-the-meter projects are forecast to account for roughly 40% of installed capacity.
  • EIR forecasts approximately 1.3 Bcf/d of incremental natural gas demand from behind-the-meter projects by 2030.
  • High-confidence project coverage declines from approximately 96% of forecast additions in 2028 to 26% in 2030.
Data center capacity growth by ISO, PJM to ISONE, 2025–2035 in GW

EIR’s analysis pulls from a variety of products including Enverus ONE.

You must be an Enverus Intelligence® Research subscriber to access this report.

EIR research reports cannot be distributed to members of the media without a scheduled interview. Journalists interested in learning more about this analysis are encouraged to use our Request Media Interview button to schedule a time to meet with one of our expert analysts, who can provide context, insight, and deeper discussion of the findings.

About Enverus Intelligence® Research
Enverus Intelligence ® | Research, Inc. (EIR) is a subsidiary of Enverus that publishes energy-sector research focused on the oil, natural gas, power and renewable industries. EIR publishes reports including asset and company valuations, resource assessments, technical evaluations and macro-economic forecasts; and helps make intelligent connections for energy industry participants, service companies and capital providers worldwide. Enverus is the most trusted, energy-dedicated SaaS company, with a platform built to create value from generative AI, offering real-time access to analytics, insights and benchmark cost and revenue data sourced from our partnerships to 95% of U.S. energy producers, and more than 40,000 suppliers. Learn more at Enverus.com.

Picture of Jon Haubert

Jon Haubert

Jon Haubert is the communications director at Enverus. Members of the media should use our Request Media Interview option on the Enverus Newsroom page to schedule an interview with one of our expert analysts.

Related News

Off the grid, on the gas
News Release
ByJon Haubert

EIR forecasts 62 GW of new U.S. data center capacity by 2030, as grid constraints drive behind-the-meter natural gas generation and demand growth.

Cheaper to buy: Gas plant acquisitions remain well below newbuild costs
News Release
ByJon Haubert

Enverus Intelligence® Research finds existing gas-fired power assets are trading at roughly half the cost of new CCGT construction, supporting incumbent valuations and challenging merchant newbuild economics.

Asia pays up after Qatari LNG loss
News Release
ByJon Haubert

EIR analysis finds Asian LNG buyers have mostly absorbed lost Qatari supply through higher-cost replacement cargoes, with demand rationing concentrated among more price-sensitive importers.

Enverus acquires A2D well log library from TGS, connecting subsurface data to energy decision workflows
News Release
ByJon Haubert

Enverus acquires the world's largest well log library from TGS, connecting three decades of subsurface data, formation tops and petrophysics to production, completions and economics workflows.

U.S. natural gas prices face power demand drag
News Release
ByJon Haubert

Enverus Intelligence Research says U.S. natural gas prices face pressure as power demand underperforms, while LNG exports remain the key offset to resilient supply.

Enverus ranks top U.S. private E&P operators
News Release
ByJon Haubert

Enverus released its annual Top 100 Private E&P Operators list, ranking U.S. private oil and gas producers by production, well count and rig activity.

Enverus acquires PDS exchange assets, expanding its operating network across U.S. energy markets
News Release
ByJon Haubert

Enverus acquires four PDS Energy Information exchange platforms, expanding secure data exchange for completions, well, production and water data.

800 VDC rewrites AI data center power economics
News Release
ByJon Haubert

Enverus Intelligence® Research analyzes how 800 VDC architecture could lower AI data center electrical capex, improve facility efficiency and reduce copper intensity.

Enverus cuts U.S. EV adoption forecast due to federal policy changes and slower market growth
News Release
ByJon Haubert

Enverus Intelligence® Research’s latest EV forecast shows how slower U.S. adoption after federal tax credit changes shifts grid load timing, regional ISO exposure and ICE vehicle displacement through 2035.

Find Out How Enverus Can Help Your Business
Subscribe to the Energy Blog

A weekly update on the latest “no-fluff” insight and analysis of the energy industry.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Get Started

Sign up for our Blog

Ready to Subscribe?

Ready to Get Started?