Texas Data Center Moratorium | Big Bark, No Bite

byCarson Kearl, Enverus Intelligence® Research (EIR) Contributor

Texas just “slammed” the brakes on data center approvals with Governor Abbott’s “moratorium.” He’s asked ERCOT and PUCT to audit every project entering the interconnection queue on tax breaks, power, water and cooling, community impact, and ownership. But half these asks are already baked into the interconnection study, and the two that aren’t, tax breaks and community impact, don’t affect whether a project can safely connect to the grid. Meanwhile, ERCOT is already working through the existing queue via Batch Zero to speed up interconnection for projects that are ready to connect.

So who loses sleep? Nobody serious. The queue already stretches to 2050, with data centers as the single biggest driver of load growth. EIR estimates ~12 GW of high-confidence load sitting in ERCOT’s queue from data centers (FIGURE 1). Well-capitalized developers are already clearing the stringent queue requirements and won’t have any trouble getting through the audit. The ones with something to worry about are the speculative projects clogging the queue, and this audit will help clean them out. And every extra day of grid uncertainty is a nudge behind the meter, so expect this to pour fuel on BTM and co-located generation that skips the queue entirely.

High confidence data center projects

This blog offers just a glimpse of the powerful analysis Power and Energy Transition Research delivers on the trending themes. Don’t miss the full picture.

Research Highlights:

  • 3Q26 Long-Term Load Forecast – Gone Behind the Meter – This report encompasses Enverus Intelligence® Research’s view on how exponential load drivers will impact our power demand forecasts from 2025-50.
  • The Long and Short of Ut(ilities) – Utility Compass 3Q26 – We screen regulated utilities by comparing the market’s Gordon-implied dividend growth against the load growth we forecast in each service territory, on the thesis that demand exposure is a good predictor of earnings growth.
  • Class VI Update 2Q26 – Submissions Dry Up, Withdrawals Pile Up – In this quarterly report series, Enverus Intelligence® Research provides an overview of recent changes to Class VI wells associated with CCUS project in the U.S. Leveraging the Enverus FOUNDATIONS® – Carbon Innovation Wells database, we cover new Class VI applications, changes to permit status, permit approvals and newly disclosed project details.

Did you know? Texas uses vastly more water raising cattle than cooling data centers, with irrigation, most of it feed for the nation’s largest herd, consuming about 9 million acre-feet a year while all U.S. data centers combined use just ~0.3% of the country’s water.

Top Three Takeaways:

1: What does Texas’s data center moratorium actually audit?

Governor Abbott has asked ERCOT and PUCT to audit every project entering the interconnection queue on tax breaks, power, water and cooling, community impact, and ownership. Half of those items are already covered by the interconnection study, and the remaining two, tax breaks and community impact, don’t affect whether a project can safely connect to the grid. ERCOT continues moving qualified projects through the queue via Batch Zero in the meantime.

2: Will the audit slow down well-capitalized data center developers?

No. Well-capitalized developers are already clearing the stringent queue requirements and won’t have trouble getting through the audit. The projects at risk are the speculative ones clogging the queue, and the audit should help clear them out.

3: How much data center load is sitting in ERCOT’s queue, and what happens if grid uncertainty grows?

EIR estimates roughly 12 GW of high-confidence data center load sitting in ERCOT’s interconnection queue, which already stretches to 2050. Every extra day of grid uncertainty nudges more developers toward behind-the-meter and co-located generation that bypasses the queue entirely.

About Enverus Intelligence® | Research, Inc. (EIR)

Enverus Intelligence® | Research, Inc. (EIR) is a subsidiary of Enverus that publishes energy-sector research focused on the oil, natural gas, power and renewable industries. EIR publishes reports including asset and company valuations, resource assessments, technical evaluations, and macroeconomic forecasts and helps make intelligent connections for energy industry participants, service companies, and capital providers worldwide. See additional disclosures here.

Picture of Carson Kearl, Enverus Intelligence® Research (EIR) Contributor

Carson Kearl, Enverus Intelligence® Research (EIR) Contributor

As an analyst on the Enverus Intelligence® Research (EIR) team, Carson is the lead on data centers and advanced energy technologies. He was previously an analyst on the macro team and has additional experience advising large industrial consumers on their energy consumption. His education in economics at the University of Alberta focused on industrial organization and power markets.

Subscribe to the Enverus Blog

A weekly update on the latest “no-fluff” insight and analysis of the energy industry.

Related Content
Enverus Intelligence® Research Press Release - Recap: How the Trump Administration is reshaping energy markets
Post
Power & Renewables
ByEnverus

Learn how utilities, hyperscalers, and developers can score assets, align stakeholders, and structure power agreements that close faster and withstand scrutiny.

Enverus Intelligence® Research Press Release - Haynesville operators calculate remaining growth
Post
Power & Renewables
ByEnverus

Learn how utilities, hyperscalers, and developers can score assets, align stakeholders, and structure power agreements that close faster and withstand scrutiny.

Enverus Press Release - E&Ps with natural gas + CCS pave way for model data center development
Post
Power & Renewables
ByEnverus

MISO hit its $10,000/MWh cap on Sept. 2 as evening load surged, solar output collapsed, and imports weakened, triggering an EEA2 alert.

Enverus Intelligence® Research Press Release - Enhanced geothermal systems: The future of reliable, green power for AI data centers?
Post
Power & Renewables
ByEnverus

A $1 million-per-MW gap separates buying gas capacity from building it. See why utilities rarely run that comparison, and what it takes to defend the answer.

Enverus Press Release - Enverus Acquires BidOut, energy’s leading AI-powered procurement platform provider
Post
Power & Renewables
ByEnverus

Most FTR losses come from sound analysis with incomplete visibility. Learn the five pitfalls that separate winning desks from ones that explain away the losses.

Enverus Intelligence® Research Press Release - Until LNG demand arrives, natural gas expected to struggle at $3
Post
Power & Renewables
ByEnverus

Enverus identified the ERCOT July 2026 coincident peak one day in advance. See how our day-ahead forecasts outperformed ERCOT during a critical summer heat wave.

Enverus Press Release - CO2 pipeline economics: The missing link
Post
Power & Renewables
ByEnverus

PJM's August 2026 base case sits above market on heat rate, with RGGI costs and capacity risk keeping the stack tight even as transmission relief arrives.

Enverus Press Release - Enverus Earns Top Workplaces Honors for Fourth Consecutive Year
Post
Power & Renewables
ByEnverus

MISO's August 2026 outlook: softer peaks vs. July, forecast converging with the market, and new Gulf Coast gas capacity reshaping South flows.

Enverus Intelligence® Research Press Release - Enhanced geothermal systems: The future of reliable, green power for AI data centers?
Post
Power & Renewables
ByEnverus

ERCOT's August 2026 risk hinges on baked-in heat, 80 GW peak scenarios, and CP exhaustion. See what could keep prices high despite a cheaper supply stack.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Sign up for our Blog

Ready to Subscribe?

Ready to Get Started?