Long-Term Load Forecast | Re-Energized Rate of Growth

byRiley Prescott

Enverus Intelligence® Research’s (EIR) long-term load forecast model considers historical drivers of power demand across the Lower 48. It forecasts the total load in the U.S. to grow 42% by 2050 from today due to population growth, increased data center demand, cryptocurrency mining growth, carbon capture and storage (CCUS), green hydrogen plant demand and electric vehicle (EV) adoption (Figure 1). SE, PJM, ERCOT and WEST are projected to experience the highest levels of load growth extending to 2050. Offsetting load growth in this figure is EIR’s behind the meter residential solar and storage forecast.

Join Enverus Intelligence® Research for the webinar, “Gas-Fired Generation | Power’s Burning Question,” and discover how natural gas will play a key role in powering the future, even as its role evolves amid the transition to renewable energy.

Data center load growth will add 153 GW of capacity by 2050. EIR believes that data center load estimates across the U.S. are overstated: load outlooks from ISOs often incorporate biases either to encourage new policy or add a margin of safety. Their model contains more realistic projections for each significant load segment using an unbiased and consistent methodology across the Lower 48.

Additionally, ERCOT base load stands out, reflecting Texas’ strong population growth and industrial base. Nevertheless, PJM and SE regions will continue to be the highest base load areas with the highest intraday variability. Exposure to large industrial load growth, such as data centers in areas such as the Dominion Zone in PJM (PJM DOM) and the North Central zone in ERCOT (ERCOT Northcentral), is the main factor driving higher load growth. EVs also have a strong impact in CAISO and the Northeastern states in ISONE, PJM and NYISO.

Research Highlights:

  • ERCOT Fundamentals – Lighting the Lone Star – Gain valuable insights into the future of the ERCOT power market with Enverus Intelligence Research’s comprehensive report, covering generation mix projections, load forecasts, power price impacts, market restructuring, interconnection queues, asset benchmarking and project siting analysis.
  • Data Center Alley – Capacity Running Out – This Fusion Insights analyzes load interconnect opportunities remaining in PJM and identifies prime locations to locate new data centers. Subscribers can download the nodal withdrawal capacity data file attachment and use Fusion to join it with our ATC or substation tables in Prism to recreate this dashboard.
  • Long-Term Load Forecast – Returning to Growth – Our long-term power demand forecast model considers historical drivers of power demand across the Lower 48 and models variables that we think will impact future load, including data centers, electric vehicles, residential solar and storage, cryptocurrency mines, green hydrogen, CCUS and electrification trends. This report analyzes the effects that these new exponential load drivers will have on our power demand forecasts from 2024-2050.

About Enverus Intelligence®| Research 
Enverus Intelligence® | Research, Inc. (EIR) is a subsidiary of Enverus that publishes energy-sector research focused on the oil, natural gas, power and renewable industries. EIR publishes reports including asset and company valuations, resource assessments, technical evaluations, and macro-economic forecasts and helps make intelligent connections for energy industry participants, service companies, and capital providers worldwide. Click here to learn more. 

Picture of Riley Prescott

Riley Prescott

As an analyst on the Enverus Intelligence® | Research (EIR) team, Riley is the lead on power demand forecasting and electrification themes. Riley has previous experience working at Alberta Electric System Operator within the forecasting and analytics team. His education is in economics and environmental science at the University of Calgary with a focus on industrial organization and statistics.

Subscribe to the Enverus Blog

A weekly update on the latest “no-fluff” insight and analysis of the energy industry.

Related Content
Enverus Press Release - Enverus releases Investor Analytics: Refined, actionable financial insights at your fingertips
Post
Power & Renewables
ByAlex Nevokshonoff, Senior Analyst, Enverus Intelligence® | Research (EIR) Contributor

Reciprocating engine backlogs surge as developers favor modular gas-fired BTM solutions for faster time-to-power and shorter lead times.

Natural gas power M&A premiums double as data center demand and capital costs transform U.S. energy market
Post
Power & Renewables, Power Trading+1
  • Utilities
ByEnverus

EIR’s PJM and MISO winter outlook: a record El Niño, capped capacity auctions, MISO scarcity risk and heat rate forecasts for Dec. through Feb.

Aging-power-plant_1418205261-1
Post
Power & Renewables, Power Trading+1
  • Utilities
ByEnverus

EIR’s ISO-NE and NYISO winter outlook: how NECEC and CHPE reshape Northeast spreads, plus RGGI costs, El Niño weather and heat rate forecasts.

EIR’s model shows powered-land can rise more than 20-fold in value as data center sites reach energization
Post
Power & Renewables, Power Trading+1
  • Utilities
ByEnverus

EIR’s CAISO and Mid-C winter outlook: how a stormy El Niño, record battery activity, EDAM vs. Markets+ and carbon prices shape Western power.

Time-to-power gap Big generation’s Achilles’ heel in the AI data center race
Post
Power & Renewables, Power Trading
ByEnverus

PJM has 113.6 GW of announced large-load capacity, far more than the 28.5 GW under construction. See what the gap means for reliability and planning.

U.S. natural gas prices face power demand drag
Post
Power & Renewables, Power Trading
ByEnverus

ERCOT data shows large loads ramping at different rates as solar and battery additions keep pace, with new supply expected to slow in 2027.

Enverus Press Release - Prioritizing renewable PPA offtaker targets proves more challenging than expected
Post
Power & Renewables
ByThomas Popa

Senate’s bipartisan permitting bill data centers grid interconnection could curb speculative queues and speed transmission buildout.

Enverus Press Release - Renewable diesel: Too much of a good thing?
Post
Data Centers, Financial Services+1
  • Power & Renewables
ByEnverus

Validate data center natural gas supply: check pipeline capacity, contracts, routing, and long‑term durability before you commit.

Enverus Press Release - How much production growth can North America deliver over the next decade?
Post
Power & Renewables
ByEnverus

See how Enverus called ERCOT's August 2026 coincident peak a day early and pinpointed the exact peak hour, beating ERCOT's own load forecast accuracy.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Sign up for our Blog

Ready to Subscribe?

Ready to Get Started?