The Chip Ceiling | PPL’s Data Center Queue Outruns Chip Supply

byThomas Popa

Third-quarter earnings season has brought a flurry of data center announcements. PPL Corp. said its pipeline of advanced-stage data center projects in PJM grew 3.5 GW to 35.3 GW in its Q3 earnings update, its 11th consecutive quarterly increase. Chip supply will make that pipeline hard to fill.

Chip supply is the largest bottleneck to AI expansion, and extreme ultraviolet (EUV) lithography is the binding step. Based on EUV output caps, Enverus Intelligence® Research (EIR) forecasts that AI chips shipped in 2030 will add 37 GW of thermal design power (TDP), the power the chips themselves draw (Figure 1). Including server and cooling loads, that supports 50.9 GW of nameplate data center capacity. The number of EUV passes required per chip will increase 4.8x from 2024 to 2030, limiting unit growth even as processing capacity rises.

PPL’s queue alone equals ~95% of that 37 GW, which is a stretch. In our 3Q26 Data Center Capacity Forecast, which draws on chip constraints, hyperscaler capex guidance and high-confidence projects, we estimate ~2 GW of capacity in the PPL zone across two campuses. Project stage and contracted offtake, not pipeline size, determine how much of the pipeline reaches commercial operation.

This blog offers just a glimpse of the powerful analysis Power and Energy Transition Research delivers on the trending themes. Don’t miss the full picture.

Strict export bans keep Chinese firms from buying complete EUV machines from ASML, so some reportedly piece together salvaged parts, but without ASML’s calibration software and assembly know-how, an EUV machine’s 100,000-plus components can’t reach the stability needed to make chips.

Research Highlights:

  • Coreweave NAV | Credit Where It’s Due
    Enverus Intelligence® Research examines CRWV using a sum of parts analysis to get a total net asset value per share.
  • AI Chip Supply | EUV Capacity Caps Power at 37.0 GW
    Enverus Intelligence® Research uncovers how extreme ultraviolet (EUV) lithography capacity will limit AI accelerator supply must be optimized between memory and logic, and ultimately caps chip power growth through 2030.
  • New York’s Storage Credit Conundrum | Delivered Reliability Doesn’t Scale With Duration
    Enverus Intelligence® Research analyzes which battery energy storage system duration – four-, six- or eight-hour – is most cost effective and delivers the most value under the New York State Energy Research and Development Authority’s Index Storage Credit solicitation.

Top Three Takeaways:

1: How much AI chip power will EUV lithography support by 2030?

Based on EUV output caps, EIR forecasts that AI chips shipped in 2030 will add 37 GW of thermal design power (TDP), the power the chips themselves draw. Including server and cooling loads, that supports 50.9 GW of nameplate data center capacity. EUV passes required per chip will increase 4.8x from 2024 to 2030, limiting unit growth even as processing capacity rises.

2: How big is PPL’s data center pipeline in PJM?

PPL said its pipeline of advanced-stage data center projects in PJM grew 3.5 GW to 35.3 GW in its Q3 earnings update. That is its 11th consecutive quarterly increase. The queue alone equals ~95% of the 37 GW of AI chip power EIR expects to ship in 2030.

3: How much data center capacity does EIR expect in the PPL zone?

In its 3Q26 Data Center Capacity Forecast, EIR estimates ~2 GW of capacity in the PPL zone across two campuses. The forecast draws on chip constraints, hyperscaler capex guidance and high-confidence projects. Project stage and contracted offtake, not pipeline size, determine how much of the pipeline reaches commercial operation.

About Enverus Intelligence® | Research, Inc. (EIR)

Enverus Intelligence® | Research, Inc. (EIR) is a subsidiary of Enverus that publishes energy-sector research focused on the oil, natural gas, power and renewable industries. EIR publishes reports including asset and company valuations, resource assessments, technical evaluations, and macroeconomic forecasts and helps make intelligent connections for energy industry participants, service companies, and capital providers worldwide. See additional disclosures here.

Picture of Thomas Popa

Thomas Popa

Thomas Popa joined the Enverus Intelligence® Research team as an associate on the AI Infrastructure team in May 2026, focusing on data center and neocloud economics and the valuation of large-load infrastructure. Thomas holds a degree in Mathematics and Economics from the University of British Columbia. With a solid foundation in quantitative modeling and economic analysis, Thomas is passionate about using data to explain how AI-driven load growth is reshaping the power sector.

Subscribe to the Enverus Blog

A weekly update on the latest “no-fluff” insight and analysis of the energy industry.

Related Content
Enverus Press Release - Enverus releases Investor Analytics: Refined, actionable financial insights at your fingertips
Post
Power & Renewables
ByAlex Nevokshonoff, Senior Analyst, Enverus Intelligence® | Research (EIR) Contributor

Reciprocating engine backlogs surge as developers favor modular gas-fired BTM solutions for faster time-to-power and shorter lead times.

Natural gas power M&A premiums double as data center demand and capital costs transform U.S. energy market
Post
Power & Renewables, Power Trading+1
  • Utilities
ByEnverus

EIR’s PJM and MISO winter outlook: a record El Niño, capped capacity auctions, MISO scarcity risk and heat rate forecasts for Dec. through Feb.

Aging-power-plant_1418205261-1
Post
Power & Renewables, Power Trading+1
  • Utilities
ByEnverus

EIR’s ISO-NE and NYISO winter outlook: how NECEC and CHPE reshape Northeast spreads, plus RGGI costs, El Niño weather and heat rate forecasts.

EIR’s model shows powered-land can rise more than 20-fold in value as data center sites reach energization
Post
Power & Renewables, Power Trading+1
  • Utilities
ByEnverus

EIR’s CAISO and Mid-C winter outlook: how a stormy El Niño, record battery activity, EDAM vs. Markets+ and carbon prices shape Western power.

Time-to-power gap Big generation’s Achilles’ heel in the AI data center race
Post
Power & Renewables, Power Trading
ByEnverus

PJM has 113.6 GW of announced large-load capacity, far more than the 28.5 GW under construction. See what the gap means for reliability and planning.

U.S. natural gas prices face power demand drag
Post
Power & Renewables, Power Trading
ByEnverus

ERCOT data shows large loads ramping at different rates as solar and battery additions keep pace, with new supply expected to slow in 2027.

Enverus Press Release - Prioritizing renewable PPA offtaker targets proves more challenging than expected
Post
Power & Renewables
ByThomas Popa

Senate’s bipartisan permitting bill data centers grid interconnection could curb speculative queues and speed transmission buildout.

Enverus Press Release - Renewable diesel: Too much of a good thing?
Post
Data Centers, Financial Services+1
  • Power & Renewables
ByEnverus

Validate data center natural gas supply: check pipeline capacity, contracts, routing, and long‑term durability before you commit.

Enverus Press Release - How much production growth can North America deliver over the next decade?
Post
Power & Renewables
ByEnverus

See how Enverus called ERCOT's August 2026 coincident peak a day early and pinpointed the exact peak hour, beating ERCOT's own load forecast accuracy.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Sign up for our Blog

Ready to Subscribe?

Ready to Get Started?