The Interconnection Queue: An Introduction

bySarp Ozkan

The interconnection queue is a collection of power generation and transmission projects requesting to connect to the power grid. Generation projects can be pre-construction, construction, built/non-operational and operating.

How do power developers submit projects to the queue?

As power developers start the process of new generation projects, they submit an interconnection request to the ISO to join the queue. An interconnection queue request would include data and documentation surrounding the project. This would include information such as project type, fuel type, net megawatt, location, operating data, synchronization date, point of interconnection, system impact study, builders, suppliers and more.

In addition to the interconnection request, a series of studies are completed to ensure the project that will potentially join the power network meets the ISO’s reliability, safety and facility standards, and is an overall best fit for the network.

What are the types of studies conducted?

  • System Impact Study (SIS) — An engineer evaluation of the point of interconnection.
  • Feasibility Study (FS) — The cost and impact a new project would have on the system.
  • Facilities Study (FAC) — The electrical configuration, price and schedule to complete interconnection.
  • Optional Interconnection Study (OIS) — The odds of other projects in the queue being withdrawn.

What has been approved and joined the power grid recently?

From 2007 to 2021, there has been an increase in renewable energy sources and demand.

graph-showing-interconnection-queue-projects-by-type-YOY
graph-showing-interconnection-queue-projects-by-type-YOY

With the increase in demand and adoption of renewable energy, the current queue is overflowing. Right now, there are more than 700 gigawatts panned across the seven ISOs with projected completion dates from 2022 to 2025.

Picture of Sarp Ozkan

Sarp Ozkan

Sarp Ozkan is VP of Commercial Product at Enverus. He joined Enverus through the acquisition of products and services from Ponderosa Advisors in 2016 and has more than 10 years of research and modeling experience in the upstream, downstream and power markets. Sarp has been a trusted energy expert for the media and for state regulatory bodies throughout the U.S. and has led consulting projects around many M&A and strategy related inquiries. He has presented at many commercial and academic conferences around the world and been published in several peer-reviewed journals. Sarp holds a Master of Science in Mineral and Energy Economics from the Colorado School of Mines, a Master of Science in Petroleum Economics and Management from the Institut Francais du Petrole (IFP School), and a Bachelor of Arts in Economics from the University of Chicago.

Subscribe to the Enverus Blog

A weekly update on the latest “no-fluff” insight and analysis of the energy industry.

Related Content

Breaking news alert on the impact on oil prices due to Israel attacking Iran
Analyst Takes Blog Topics
ByAl Salazar, Enverus Intelligence® Research (EIR) Contributor

In response to today's announcement that EOG Resources would acquire Encino Acquisition Partners for $5.6 billion, Andrew Dittmar, principal analyst at Enverus Intelligence® Research provided this commentary explaining the deal's significance.

nuclear-worker
Energy Transition
ByAmyra Mardhani

Westinghouse’s CEO revealed talks with U.S. officials this week to deploy 10 large nuclear reactors as part of a broader push to back nuclear energy as data centers drive energy demand skyward.

Enverus and Pexapark Press Release - Enverus Enhances Global Trading & Risk Platform with Pexapark’s Benchmark Renewables Pricing and Market Intelligence
Minerals
ByPhillip Dunning

The headline-grabbing $4.1 billion merger between Viper Energy and Sitio Royalties isn’t just another deal—it’s a signal flare for the entire minerals market.  Andrew Dittmar, principal analyst at Enverus Intelligence, calls it “a rare public mineral merger,” in his latest...

Enverus_Press_Release_Fundamental_Edge_1Q25_Thumbnail
Energy Analytics Operators
ByEnverus

The following blog is distilled in part from Enverus Intelligence® Research (EIR) publications.  After nearly a decade on the sidelines, EOG Resources has made a bold return to the M&A arena with its $5.6 billion acquisition of Encino Acquisition Partners (EAP)....

Enverus_Press_Release_Data_Centers_Thumbnail.png
Energy Transition Power and Renewables
ByRobin Grathwohl

At Enverus, we empower energy innovators with intelligent software that transforms complexity into clarity and decisions into results. Using our PRISM platform, we analyzed how our customers are outperforming the market in building successful power and renewables projects.   By comparing...

Enverus Intelligence Research Press Release - Upstream M&A sails to $17 billion in 1Q25
Energy Analytics Operators
ByEnverus

The following blog is distilled from Enverus Intelligence® Research (EIR) publications. As the upstream oil and gas sector faces mounting pressure from rising costs and dwindling Tier 1 inventory, the need for smarter, faster and more efficient development strategies has never...

Enverus Press Release - The Denver Post names Enverus a Top Workplace in Colorado
Energy Analytics
ByEnverus

The first quarter of 2025 has seen a remarkable surge in oil and gas mergers and acquisitions (M&A) within the upstream oil and gas sector, with transactions totaling $17 billion. This dynamic environment presents both challenges and opportunities for small...

Enverus Intelligence Research Press Release - Upstream M&A sails to $17 billion in 1Q25
Power and Renewables
ByJacob Papka

The Electric Reliability Council of Texas (ERCOT) manages one of the most dynamic and complex power grids in the United States, serving over 26 million customers across Texas. Forecasting energy demand and supply in this region is no small feat....

Enverus Blog - The Texas power market evolution
Energy Transition
ByElliot Ryland

In response to the data center boom, the Texas House recently passed Senate Bill 6, which promotes oversight of large loads (exceeding 75 MW), particularly those with behind-the-meter generation.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Let’s get started!

We’ll follow up right away to show you a quick product tour.

Sign up for our Blog

Register Today

Sign Up

Power Your Insights

Connect with an Expert

Access Product Tour

Speak to an Expert